• No results found

Reclaimed asphalt processing and management at the mixing plant

N/A
N/A
Protected

Academic year: 2021

Share "Reclaimed asphalt processing and management at the mixing plant"

Copied!
21
0
0

Loading.... (view fulltext now)

Full text

(1)
(2)

We

contribute to construct high quality roads

but at the same time we contribute to demolish the

(3)

We enhance the demolition of the roads in case

they have reached the end of their service life

and can no longer perform properly, so instead

of making continuous local maintenances to the

roads (something which is costly), it is better to

remove the existing pavement surface and

(4)

What about the environment?

To the landfill

(5)

WP4 Objective

To collect knowledge to support the optimum use of RA with

respect to various issues like:

• RA production

• RA processing and handling

• RA introduction in the mixing plant or mixing process

Re-Road Objective

Facilitate the highest possible potential of recycling of reclaimed

asphalt and to support recycling of RA in high percentages in

surface layers in heavily trafficked roads in Europe.

(6)

Milling Operation

Excavation Operation

(In the case of minor deformation, cracking ..etc)

(7)

Cold milling Hot milling

In this case, the overall pavement surface will be removed Task 4.3

Not

(8)
(9)

Receiving and rough sorting according to the following incoming

qualities:

Milled materials

Milled materials Excavated materialsExcavated materials

Separation

Removal of undesirable materials like surplus, gravel, soil, etc

1

(10)

Crushing and Screening 3

Milled materials

Milled materials Excavated materialsExcavated materials

Storage Process 4

Homogenization 5

(11)
(12)
(13)

Mixing directly in the mixer Mixing in the heating conveyor

Mixing in the drying drum Mixing in the parallel drum

(14)
(15)
(16)

The recycling RA in new hot-mix asphalt is common practice in Germany.

(17)
(18)

Du to the funds received from Re-Road project, we

could recycle “for the first time” asphalt mixtures with 50% RA in Slovenia

20% (m/m) asphalt recycling No recycling

Operation and quantity Costs in Euro Operation and quantity Costs in Euro

cold milling 1000 m2of

asphalt layer 6 cm deep

2170 cold milling 1000 m2of

asphalt layer 6 cm deep

2170 transport of 60 m3RAP distance 10 km 425.4 transport of 60 m3RAP distance 10 km 425.4

Crushing 60 m3RAP 812.4 Stockpile fee and tax for

60 m3RAP 510 Production of 300 m3 asphalt containing 20% RAP 43800 Production of 300 m3

asphalt without RAP

54750

Sum for 20% RAP 47207.8 Sum without RAP 57855.4

(19)

Summary and Conclusion

The attempts have been made to incorporate RA into HTM mixes show that a moderate RA incorporation of (20-30%) does not affect the mixes composition or properties too much.

At higher RA materials incorporations (between 30-50%), the mechanical properties are more sensitive.

The technology is available regarding high percentage of RA involvement, but can be improved and optimized further.

(20)

References

• Handbook for Recycling of Asphalt (2004), Vägverket, Publication -No. 2004-91, In Swedish.

• Dina Kuttah, Erik Nielsen, Anders Pettersson and Marjan Tusar (2012): “Production and processing of reclaimed asphalt - Selected case studies”, Deliverable 4.4 Re-Road Project.

• Marjan Tušar, Erik Nielsen, Fatima Batista, Maria de Lurdes Antunes, Konrad Mollenhauer, Stefan Vansteenkiste, Ian Carswell, Dina Kuttah, Leif Viman, Andreas Waldemarson (2012): “RA optimization in asphalt plant mixing”, Deliverable 4.5, Re-Road Project.

(21)

?

?

References

Related documents

Vi tror att det kan vara så att deltagarna tycker att de från början har haft ett beteende som gör de anonyma och att de därför inte ändrat sättet de använder till

2.3 A new test to study the flow of mixtures at early stages of compaction In this paper, similar to the FT setting, a uniaxial servo-hydraulic testing machine with 100kN

" Minimize transportation distances by updating collection routes. This should be done in combination of maintaining the sell strategy towards costumers in neighboring

There is currently no way for Dynapac to track which screwdrivers are used and how often, resulting in every screwdriver being calibrated on a set time interval instead of when

Keywords: Life Cycle Assessment; feedstock energy; asphalt binder additives; mass-energy flows; bitumen healing; wax;

4 Distance will double as loaded trucks will roll to the required site and unloaded when coming back.. The production energy of aggregate was 51 GJ. As no additives were

Recurrent processing has been proposed to be the activity causing VAN (Railo, Koivisto, & Revonsuo,.. 2011) thus further supporting recurrent processing’s role in

In trying to explore the potential of 3PL involvement in the internal logistics department of an asphalt production project, proven by the theoretical and empirical