• No results found

Lead time analysis and reduction at Alfa Laval DC Lund

N/A
N/A
Protected

Academic year: 2021

Share "Lead time analysis and reduction at Alfa Laval DC Lund"

Copied!
4
0
0

Loading.... (view fulltext now)

Full text

(1)

1

Lead time analysis and reduction at Alfa

Laval DC Lund

Nils Wilhelmsson & Erik Dahlberg

Lund University, Faculty of Engineering Autumn 2012

Introduction

Company background

Alfa Laval is currently the world leader in heat transfer products but the company is also active in two other areas; separation and fluid handling (Alfa Laval, 2013a). Alfa Laval DC Lund is one of Alfa Laval’s distribution centers which provide the aftermarket with spare parts. The spare parts that Alfa Laval DC Lund supplies are used for the heat transfer business unit of Alfa Laval. DC Lund operates as a distribution center in the traditional sense but products are also manufactured on the same site. The ERP system Movex is used at all distribution centers globally as it is thought to have good support for warehousing.

The large majority of the articles handled at Alfa Laval DC Lund are plates and gaskets but there are also other articles such as bolts, frames (the blue parts in Figure 1), pumps etc. The size of the plates varies from 10x35cm to 120x300cm which demands flexibility in both production and in the warehouse. The heat exchangers work by running warm and cool liquid every other plate as can be seen in Figure 1. Plates are mounted on hangers and the heat exchanger is held together under a high pressure with large bolts (not shown in the figure).

(2)

2

In Figure 2 a heat exchanger plate can be seen. This particular plate has a glue-less clip-on gasket which means that the gasket is held in place by the black clips that can be seen as black extensions of the gasket at the edges of the plate. There is also another kind of gasket that is mounted using glue.

Figure 2: Heat exchanger plate with clip-on gasket (Alfa Laval, 2013b).

Order process

The order handling process starts when Alfa Laval DC Lund receives an order from the end-customer directly or from a sales office. If an order that arrives only contains articles that are held in stock, the articles are picked, packed and the order is shipped. If the order contains products that need to be manufactured the order process is different as can be seen in Figure 3. The parallelograms in the figure represent a registered event in Movex.

Figure 3: Manufacturing order process at Alfa Laval DC Lund. MO is manufacturing order

and CO is customer order.

Production

The production is divided into three work centers; C10, R10 and X10. These work centers are also present in Movex and contains different work operations in production. Different products require different work operations, meaning that all operations in a work center do not have to be performed. The C10 work center handles punching of article numbers as well as the mounting of the clip-on gaskets to plates. If any other operations are needed the production is carried out in the X10 work center. This includes punching of holes and article numbers, projection welding of hanger reinforcements, spot welding of plate strengtheners (only used on older plates), applying glue, mounting gaskets, putting the plates in the oven as well as inspecting the gaskets after the oven. Some gaskets that are used for mounting using glue need to be roughened, this operation is performed in the third work center, R10.

MO suggestion automatically

created

MO released MO entry date & time CO received

CO entry date & time

MO is printed and delivered to production Picking done Actual start date Production finished and order is put away Actual finish date

Picked, packed and shipped Production

(3)

3

Problem formulation

A problem today is that the time it takes Alfa Laval DC Lund to produce and send an order to a customer is perceived as too long. It is not known where in the process the majority of time is spent as well as what can be done to reduce it.

Purpose & Objective

The purpose is to perform a thorough analysis of the lead time for manufacturing orders from that the customer order arrives at Alfa Laval DC Lund to the customers theoretically receive delivery (based on predefined transportation/shipment time). The analysis should yield an overview of the lead time and pinpoint areas of improvement potential. A solution that will reduce lead time for manufacturing orders should be created and implemented. After the implementation of this solution further research areas should be identified and presented.

The main delimitations

 Manufacturing orders connected with a customer order will be in focus  No changes to suppliers, purchasing, sales or customer behavior will be made  Analysis will be limited to Alfa Laval DC Lund

Analysis and improvements

Data has been gathered through interviews, observations, literature studies and from measuring processes and extracting data from the ERP system’s database. To provide an overview of the lead time it was divided into six distinct measurements. In Figure 4 the overview of these lead time measurements can be seen. The values behind this figure have been calculated using the data extracted from Movex. The sizes of the measurements in the figure represent their part of the total lead time. This graphical overview is a powerful tool in determining where the largest parts of the lead time are positioned. It is also effective in providing an understanding of the lead time process. The measurement T2, which is supplier lead time, is the largest part of the total lead time. After this transportation time and the measurement T3, which is waiting time to start production, are roughly equal. Of these three measurements, which have the largest impact on the lead time, T3 is the only one within the scope of the project and it has therefore been analyzed further.

Figure 4: Overview of measurements, sizes roughly matching average times.

T1 T2 T3: 4,1 days T4 T

5 Transportation time

Internal lead time

Total lead time: 15,1 days

At customer CO entry MO released Material available Production start Production finished MO shipped

(4)

4

In the further analysis it was concluded that T3 could be divided into two parts; planned waiting time to start production and difference in actual and planned production time. Analysis of these revealed that planned waiting time to start production was due to capacity constraints in production and the difference in actual and planned production time was due to wrong production lead time in the ERP system Movex. To reduce the planned waiting time to start production an action plan to increase flexibility in the workforce was created. This solution will however take several months to finalize and has therefore been left to Alfa Laval DC Lund. To reduce the difference in actual and planned production lead time the production lead time in Movex was adjusted after identifying which products that should be changed. The products that could not be identified initially will be adjusted continuously. Computer based tools has been created and left to Alfa Laval DC Lund for this purpose.

Results

When all products with incorrect production lead times have been adjusted the benefits of the implemented solution will be a 30% decrease in internal lead time when material is available from start and a 10% decrease in internal lead time when material is not available from start. This will in turn generate a total of approximately 14 000 euro per year in savings from less tied up capital and profits from earlier revenue. The initial adjustment of production lead times has already yielded a significant lead time reduction. The analysis has also yielded information that Alfa Laval DC Lund can use to start new projects with the purpose to reduce lead time and/or improve their business.

Conclusions

It has been concluded that human interference with as well as wrong data in ERP systems drive lead times. The research also demonstrates the importance of working with the ERP system and using its features in a correct way instead of working beside and overriding it.

Scientific contributions

The results of this research are not generalizable, however this report provides a good methodology of how the lead time both efficiently and effectively can be analyzed and improved in businesses. If a project should be initiated with the intent to reduce lead time this is an efficient way of structuring the project. To perform the analysis the lead time should be divided into different but not to small and detailed processes. This will provide an overview (graphical is preferred) of the lead time and yield areas that could be improved. These areas should then, if possible, be broken down into even smaller processes. A root cause analysis should then be performed to find a solution that reduces lead time.

Further research areas

There are several areas that Alfa Laval DC Lund can and should improve some of which are:  Reduce supplier lead times

 Correct wrong data in Movex

 Digitalize paper handling in production

 Earlier and automated release of manufacturing orders to production

References

Alfa Laval, (2013a). About Alfa Laval. [Online] Available at: http://www.alfalaval.com/about-us/ [Accessed 2013-01-21].

Alfa Laval, (2013b). Products. [Online] Available at: http://www.alfalaval.com/solution-finder/products/ [Accessed 2013-01-21].

Figure

Figure 1: Functional overview of a heat exchanger (Alfa Laval, 2013b).
Figure 3: Manufacturing order process at Alfa Laval DC Lund. MO is manufacturing order
Figure 4: Overview of measurements, sizes roughly matching average times.

References

Related documents

För snart tre år sedan beslutade kommunfullmäktige att en miljö- vårdsplan för Lund skulle utar- betas.. De borgerliga partierna tyckte inte att någon sådan

Målet med detta examensarbete är att identifiera de faktorer i order- och leveransprocessen som kan leda till att kunden gör en reklamation som orsakats av att fel delar skickats

The research lessons consisted of exercises inspired by spoken word poetry, such as watching a clip of a spoken word artist performing their poem, analyzing and imitating that model

O Beträffande likviditetsutvecklingen hänvisas till finansie- ringsanalysen och kommentar l till moderbolagets ba- lansräkning. O Övriga kortfristiga skulder innefattar bl

Ett stort problem för lantbruket är det globala överskot- tet av skummjölkspulver och smör. EG-kommissionen har sedan några år tillbaka vidtagit åtgärder för att

Inom ramen för regeringens utbyggnad av alkohol- produktionen för motorbränsle levererade Alfa-Laval ett stort antal separatorer och värmeväxlare.. Företaget fick också

Även fö rsäljnin gen av utrustning till destilleriindustrin (etanol p rod uktio n) i Brasilien har va rit fra mgångsrik. Detta har medfört att den lokala tillverkning- en i

A case study of a firm (Alfa Laval) presents a manufacturing example of on-the-job training program and observes the impact on employees’ productivity; has been done