The North Bothnia Line

Supplier dialogue before project

planning of construction documents

Dåva-Skellefteå

October 2020

Helena Westberg, Anders Bennitz and Kenneth Strandh

(3)

Agenda

• Brief presentation of the supplier (5 min)

• Current situation in the project The North Bothnia Line, The Swedish Transport Administration (20 min)

• The supplier's thoughts on how we can conduct the project planning in an efficient manner (30 min).

• Mutual discussion on:

‒ Packaging of assignments and interfaces

‒ Times (purchase schedule, tender count, times before the start of the assignment, execution times)

‒ Qualification requirements - evaluation (added value)

‒ Current market situation

(4)

Brief presentation of the supplier

5 min

(5)

The current situation of the program The North Bothnia Line

(The Swedish Transport Administration - Trafikverket)

20 min

(6)

This is The North Bothnia Line

• 270 km new coastal railway between Umeå and Luleå

• Single-track railway with meeting stations, about 10 km apart

• Designed for 250 km/h

• 22 freight trains and 44 passenger trains/day

• Budgeted cost SEK 29 billion (2013-06)

(7)

We will build

• 270 km railway

• 550 km of roads (public roads, replacement and service roads)

• 250 bridges

• 2-5 tunnels

• 3 travel centers (Skellefteå, Piteå and Luleå)

• 4-5 regional train stations (Sävar, Robertsfors, Bureå, Byske)

(8)

This is what we do now

Umeå-Dåva, about 13 km

2 construction contracts are in progress

– Ground- /Soil reinforcement – Bridges

In 2021, the tunnel and land contracts will be procured

Dåva-Skellefteå, about 120 km

Completion of the railway plans

Preparing for procurement for the detail design

(9)

Timetable, Umeå-Skellefteå

2024-2030

Dåva-Skellefteå

2020-2024

Umeå-Dåva

PRODUCTION

RAILWAY PLANS

2020-2021

Railway plans legally determined

2016-2020

Consultation with local residents, businesses and authorities

2018-2020

Umeå-Dåva

2021-2026

Dåva-Skellefteå

2024

Dåva-Skellefteå

TRAFFIC START 2015-2020

Field inventories, geotechnics, archeology, line studies, environmental impact assessments, and

design

2030

Umeå-Dåva

DESIGN

(10)

Targets for procurement strategy

• Large design contracts - minimize the number of interfaces, reduce the need for coordination, uniform solutions.

• Mixed contract sizes - the majority are large contracts in the range of SEK 200 - 1,500 million.

• Strive for mass balance

• Standardized bridge constructions - minimize the number of unique constructions, increase quality while reducing the time for design, procurement and construction

• A summary of our procurement strategy can be found on our website (also in English)

(11)

2021

(12)

Upcoming procurements

Detailed design

Dåva-Skellefteå (2020-2021)

Fieldwork geotechnics 2 contracts

Land works and facility 5-6 contracts

Preparatory detailed design + BEST 1+1 contracts Standardized bridge construction 1-2 contracts

(13)

2020

Nov Dec Jan

2021

Feb Mar Apr May Jun Jul Aug Sep Oct

C

NBK203 - Construction documents facility

Ytterbyn-Grandbodarna NBK204 - Construction documents

facility

Grandbodarna-Södra Tuvan

NBK207 - Construction documents facility

Gryssjön-Ytterbyn

NBK206 - Construction documents facility

Sundbäck-Gryssjön

NBK208 - Construction documents BEST

Sundbäck-Skellefteå

2023

Gryssjön

20232021

NBK205 - Construction documents bridge Skellefteå älv

NBK202 - Construction documents facility

Norra Tuvan - Skellefteå C NBK302 -Field geotechnics

Gryssjön – Ytterbyn

NBK306 - K-report Standard bridges NBK301 -Field geotechnics

Sundbäck – Gryssjön

(14)

The supplier's thoughts on how we can conduct the design in an

efficient manner.

30 min

(15)

Mutual discussion and questions

(16)

Thank You!

(17)

Contact

trafikverket.se/norrbotniabanan

trafikverket@trafikverket.se

0771-921 921

References

Related documents

We seek to give an overview of diferent issues of history and memory that are at stake, and diferent actors and institutions involved in the production of memory, the development

The thesis brings together and discusses several theories that might explain the access and use of public spaces from a gender perspective; planning theory, theories about

However, note that substructure (tunnels, bridges, track foundations) and power, signalling and telecom systems are not included.. The figure shows some of the most

The contribution from railway infrastructure to the total environmental impact for railway transport services is presented here in a transport scenario.. 10

Sustainability in building construction -- Framework for methods of assessment for environmental performance of construction works -- Part 1: Buildings. International Organization

Three different types of damping control devices were introduced in this report, the fluid viscous damper (FVD), the magnetorheological (MR) damper and the tuned mass damper

In the serviceability limit state; when a composite structure is subjected to positive bending moment, the concrete is in compression and the steel is mostly in

The project planning will be carried out in large project planning assignments to minimize the number of interfaces, reduce the need for coordination and for easier steering