• No results found

Progress report no 10.pdf Pdf, 435.7 kB.

N/A
N/A
Protected

Academic year: 2022

Share "Progress report no 10.pdf Pdf, 435.7 kB."

Copied!
10
0
0

Loading.... (view fulltext now)

Full text

(1)

Lake Turingen Remedial Project

Isolation of mercury contaminated sediment

Tool for monitoring production of artificial sediment – retrieved February 2003 (photo J. Skarp)

LIFE ENVIRONMENT

Project No. LIFE98 ENV/S/000477

Progress Report No. 10 September 12, 2003 Municipality of Nykvarn

Sweden

(2)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 2 (8)

LIFE Project Number

LIFE98 ENV/S/000477

PROGRESS REPORT No. 10

Covering project activities from 01/01/2003 to 30/06/2003

Reporting Date

12/09/2003

LIFE PROJECT NAME

Lake Turingen Remedial Project

Project Data

Project location: Nykvarn, Sweden

Project start date: 01/02/1998 Project end date:

Extension date:

01/02/2004

30/04/2004 (Final report)

Total Project duration (in months):

Extension duration (in months):

72 months 3 months Total revised budget: SEK 58,250,000.00

EC contribution: € 890,422.15

(%) of total costs: 13.33

(%) of eligible costs: 27.62

Beneficiary Data

Name of beneficiary: Municipality of Nykvarn

Contact person: Fredrik Norberg

Postal address: SE-155 80 Nykvarn, Sweden

Visiting address: Centrumvägen 24, SE-155 80 Nykvarn, Sweden

Telephone: +46 8 552 487 00

Fax: +46 8 552 489 99

E-mail: fredrik.norberg@nykvarn.se

(3)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 3 (8)

Website: http://www.nykvarn.se

(4)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 4 (8)

TABLE OF CONTENTS

Executive Summary ...5

Project Management ...5

General...5

Legal Issues...5

Technical Development ...5

Investigations ...5

Environmental monitoring ...5

Remedial Construction...6

Problems encountered or foreseen...7

Dissemination...8

Expected progress up to 31/01/2004 ...8

Financial situation...8

Scheduling ...9

Statement of submission...10 Appendices

Expenditure report ...Appendix 1 Comparison between previous and current budget ...Appendix 2 First page – thesis report on GIS application for Turingeån...Appendix 3

(5)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 5 (8)

Executive Summary

The primary objective of the Lake Turingen Remedial Project is to isolate between 90 and 95% of the mercury-contaminated sediments found in the lake and in the river Turingeån from the aquatic environment. The most important activities and results from the reporting period ended June 30, 2003 are:

Continuation of Stage 2 construction (placement of artificial sediment on lake bottoms)

Additional data showing positive results from Stage 1 construction (capping with sand and gravel of lake bottoms near the mouth of the river)

Preliminary data indicating positive effects from Stage 2 construction

Complementary financing (7.85 MSEK) received from Swedish Environmental Protection Agency.

Project Management

General

The project management group – consisting of the project manager, project administrator, financial administrator, dissemination coordinator, and task managers – did not hold any meetings during the reporting period. Instead, project management was handled by a committee composed of the project manager, construction task manager and environmental monitoring task manager.

Legal Issues

The legal issues task has been terminated and no other legal issues are anticipated.

Technical Development

Investigations

The investigation task has been terminated and no other investigations are anticipated.

Environmental monitoring

Environmental effects from Stage 2 construction are being monitored in accordance with planned activities. As previously reported, results continued to confirm a decrease in the flow of mercury-contaminated particles from the area that was capped at the south end of the lake during Stage 1.

(6)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 6 (8)

Since Autumn 2002, there appear to have been both further reductions in absolute levels of mercury and a change in the seasonal trend of this data. These effects may be related to Stage 2 remediation, which started in October 2002, see Figure 1. Other monitoring activities continue as planned and adjustments will be made as dictated by progress in remedial

construction and results obtained through previous monitoring. The next monitoring report will be issued after completion of construction, i.e. at the end of 2003.

Figure 1. Mercury in falling sediment. Horizontal line lengths represent periods during which sediment was collected.

As mentioned in previous reports, the monitoring program has indicated continued inflow of small amounts of mercury from upstream areas via the river Turingeån. During the current reporting period, all relevant data from various investigations in and along the river were entered into a geographic information system (GIS) as part of an undergraduate thesis at Uppsala University School of Engineering, see Appendix 3.

Remedial Construction

During the reporting period, the remedial contractor made a number of small changes to improve its equipment for producing artificial sediment. As reported previously, the actual distribution of artificial sediment produced during 2002 was less uniform than expected. To investigate this matter, capping of four additional test areas was performed at the end of May 2003. Test results indicated that uniform capping could be performed, and full-scale capping of lake bottoms resumed a few days later.

Hg in falling sediment (µg/g dw)

-1 0 1 2 3 4

Surface Bottom

1999 2000 2001 2002 2003

SN upstream C Station L downstream M

1999 2000 2001 2002 2003

1999 2000 2001 2002 2003

1999 2000 2001 2002 2003

(7)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 7 (8)

By the end of June 2003, about 80% of the total mass of capping materials had been expended. Supplemental financing from the Swedish Environmental Protection Agency will enable production to proceed until 150% of the original amount of capping material has been used. Work is now planned to continue throughout the summer and early Autumn of 2003.

Project management expects therefore that the original goals concerning cap thickness will be met at that time, see Figure 2.

Figure 2. Planned thickness of artificial sediment cap.

Problems encountered or foreseen

Work done during the reporting period has continued to indicate the ability of the contractor to produce artificial sediment and place it at a desired location. Results from the latest tests

(8)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 8 (8)

showed that equipment and raw materials as well as procedures appear to function in relatively good accordance with design parameters. No further complications are expected.

Dissemination

Dissemination activities during the reporting period included:

Updating of the project’s Internet web site (http://www.turingen.com)

Several visits to the site by interested parties.

Expected progress up to 31/01/2004

During the next (and final) reporting period, significant progress is expected in the following areas:

Completion of production capping with artificial sediment

Issuance of sixth project newsletter

Additional site visits.

No progress report will be issued for this period. Instead, the project’s final report will be published by April 2004, at the latest.

Financial situation

The financial status of the project per June 30, 2003 is shown in the expenditure report in Appendix 1. Approximately 93 % of budgeted funds have been expended, and all budget lines are in general accordance with the budget as approved by the European Commission. Data shown in Appendix 1 do not reflect supplemental financing in the amount of 7.85 MSEK that was received from the Swedish Environmental Protection Agency at the end of June 2003. All funds made available to date have been consumed; the municipality is currently financing all project activities until final resolution with the various financiers.

In accordance with a letter from the Commission dated June 12, 2003, the effect of the supplemental financing on the project budget is shown in Appendix 2. 79 % of the new funds (6.2 MSEK) will be used for additional remedial construction as described above, including decommissioning costs. Lesser amounts will be used to cover increased costs for project management, facilities rental, external assistance (environmental monitoring and construction monitoring) and dissemination. These latter costs are mainly due to the previously approved one-year extension of the project and/or the increased amount of remedial construction. At this late date in the project, it is also apparent that expenditures for equipment and other costs will be less than expected.

(9)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 9 (8)

Scheduling

No further changes to the project time schedule are expected.

(10)

LAKE TURINGEN REMEDIAL PROJECT Progress Report No. 10

LIFE98 ENV/S/000477

2003-09-12 Page 10 (8)

Statement of submission

The undersigned submits this progress report on the date shown below and asserts that it accurately represents the status of the project on June 30, 2003 in all pertinent regards.

Nykvarn, Sweden September 12, 2003

Ronald Bergman Project Manager

References

Related documents

The concept can be used to continue the development of the dashboard for risk man- agers, but it can also be used, together with the overview of information visualization and

Nej ast jší odpov dí u muž , pro považují spole nost za eticky jednající bylo, že se drží Etického kodexu, dodržuje Ekologické desatero, zajímá se o sociální odpov

Sekce obsahuje hned několik položek menu, mezi které patří přidání nové firmy, přidání adresy již ke stávajícím firmám, v případě, že se firma rozrostla o

It should be noted that the Reference phase is based on techniques and data from (a) the ongoing monitoring program currently used for evaluation of the remedial works completed

Since the use of digital tools such as Building Information Modeling (BIM), digital project platforms and digital meetings are nowadays important in the communication

During this process, the theoretical framework changed from initially elaborating on the safety manager as a change agent in an organisation to looking at the role as a

Varför dessa funktioner finns är för att det utgör grunden till själva applikationen då appen behöver kunna hantera informationen som kommer läggas i en databas...

In this section, the future work will be discussed. To be able to draw more conclusions and identify patterns more projects should be studied. More people should be interviewed,