• No results found

Limitations set by the distribution network against the large-scale integration of distributed energy resources

N/A
N/A
Protected

Academic year: 2021

Share "Limitations set by the distribution network against the large-scale integration of distributed energy resources"

Copied!
1
0
0

Loading.... (view fulltext now)

Full text

(1)

Performance index

Amount of generation Existing level

Improvement Acceptable deterioration

Unacceptable deterioration

Hosting capacity

Limit 0 10 20 30 40 50 60 70 80 90 100

0 50 100 150 200 250 300 350 400

Generator rating (kVA)

Current (A)

Limitations set by the Distribution Network against the Large-Scale Integration of DER

Hosting Capacity: a tool that allows, for the first time, a fair and open discussion between the different stakeholders and a transparent balancing between their interests :

 Acceptable reliability and voltage quality for all customers;

 No unreasonable barriers against new generation;

 Acceptable costs for the network operator.

Conclusions

Most distribution networks can cope with several tens of percent of DER without significant additional investment.

However, every case is unique and knowledge of the hosting capacity is needed in all cases.

Authors:

Math Bollen, Fainan Hassan, Yongtao Yang, STRI AB, Sweden.

http://www.stri.se

Examples

The risk of overloading reduces as long as the generation is less than the sum of minimum and maximum load.

First approximation: the losses get smaller as long as the average generation is less than twice the average load.

New harmonic resonances may occur due to the capacitive character of the interface for some of the DER units.

Unacceptable distortion may occur for frequencies above 2 kHz already for a small number of units.

This is based on “save limits” but higher levels may be acceptable.

Basic principle of the hosting capacity approach: compare the network performance with a limit.

Generator halfway a 2-km 230V feeder from a 200kVA, 5% transformer

Downstream faults

Upstreamfaults Hosting capacity Minimum setting margin

Red: single-phase fault Green: phase-to-phase fault Blue: two-phase-to-ground fault Black: three-phase fault

0 2 4 6 8 10 12

235 240 245 250 255

Wind power rating at 10 kV (MW)

Voltage magnitude (V)

Maximum voltage for a LV customer due to wind power at MV. Hosting capacity for 2 overvoltage limits and 4 statistical limits.

100% 99.99% 99.9% 99%

1.05pu 2 MW 3 MW 3.5 MW 5 MW 1.08pu 7 MW 8 MW 9 MW 10.5 MW

Hosting capacity

References

Related documents

46 Konkreta exempel skulle kunna vara främjandeinsatser för affärsänglar/affärsängelnätverk, skapa arenor där aktörer från utbuds- och efterfrågesidan kan mötas eller

Both Brazil and Sweden have made bilateral cooperation in areas of technology and innovation a top priority. It has been formalized in a series of agreements and made explicit

The increasing availability of data and attention to services has increased the understanding of the contribution of services to innovation and productivity in

Generella styrmedel kan ha varit mindre verksamma än man har trott De generella styrmedlen, till skillnad från de specifika styrmedlen, har kommit att användas i större

Parallellmarknader innebär dock inte en drivkraft för en grön omställning Ökad andel direktförsäljning räddar många lokala producenter och kan tyckas utgöra en drivkraft

Närmare 90 procent av de statliga medlen (intäkter och utgifter) för näringslivets klimatomställning går till generella styrmedel, det vill säga styrmedel som påverkar

I dag uppgår denna del av befolkningen till knappt 4 200 personer och år 2030 beräknas det finnas drygt 4 800 personer i Gällivare kommun som är 65 år eller äldre i

Calculating the hosting capacity for a specific feeder requires a large amount of data, on existing voltage variations, on variations in consumption of active and reactive power,