• No results found

Amended Authorization for the Rio Grande Reservoir, January 9, 1986

N/A
N/A
Protected

Academic year: 2021

Share "Amended Authorization for the Rio Grande Reservoir, January 9, 1986"

Copied!
6
0
0

Loading.... (view fulltext now)

Full text

(1)

COLORADO WATER CONSERVATION BOARD Department of Natural Resources

721 State Centennial Building 131 3 Sherman Street Denver, Colorado 80203 Phone: (303) 866-3441

STATE OF COLORADO

Richard D. Lamm Governor M E M O R A N D U M J. William McDonald Director David W. Walker Deputy Director TO: Members, CWCB

FROM: Bill McDonald

DATE: January 9, 1986

SUBJECT: Agenda item 14d, January 16-17, 1986, Board Meeting--Amended Authorization for the Rio Grande Reservoir

The staff recommends that the Board recommend to the General Assembly that the previous authorization for the subject project be amended per the terms and conditions set forth in the enclosed project summary.

JWM/gl

Enclosure: as stated

721 ai/14d

(2)

Introduction

721 State Centennial Building 1313 Sherman Street

Denver, Colorado January, 1986

Rio Grande Reservoir Project (San Luis Valley Irrigation District)

Draft 1/8/86

In 1982, funds in the amount of $1,134,500 were authorized for the Rio Grande Reservoir project, which reservoir is owned by

the San Luis Valley Irrigation District. Of this amount,

$619,500 (54.6%) was stipulated to be nonreimbursable and the remaining $515,000 (45.4%) was made available as a loan at 5 percent repayable over 40 years.

Design engineering was subsequently completed by the

District's engineer. The first of two contracts for the project

was awarded by the District in August of 1982 to rehabilitate the

gates and the outlet works of the dam. The first contract was

substantially completed in March, 1984, and the engineer certified that the work complied with the plans and

specificationss The second contract for raising the dam and

improving the spillway was awarded by the District in 1983 and all work under that contract was completed and accepted in that same year.

(3)

Problem

Subsequent to the acceptance of the outlet works and gates rehabilitaton work by the District's engineer, leakage around the gates increased greatly and a newly installed steel plate liner tore free from an outlet tunnel wall. In addition, it appears that the operating mechanisms for the gates are in need of additional adjustments and/or repairs.

Project Review

As a result of the outlet works' problems that have arisen since March, 1984, the Board has asked the District to require the contractor to extend its performance bond on the project through December, 1986, which has been done. The Board also required the District to retain a new engineering firm

specializing in gate rehabilitation to assess the proble~s which have arisen and to recommend solutions thereto. The new

engineers have made field inspections for such an assessment and have informed the District of their findings. The information furnished by the new engineers is the basis for recommendations on this project.

The Board an~ the District have under investigation the circumstances concerning the problems which have been

encountered. The Board has advised the District that it must

(4)

-2-take any and all steps necessary to protect all avenues of possible recovery which the District may have against the

original engineer, the contractor, and the issuers of the surety bonds taken out by the contractor pending the results of the investigation. In addition, 'the Board has ask.ed the Attorney General to work with the District's attorneys to assist in determining what steps should be taken to protect possible avenues of recovery against the original engineer and/or the contractor.

Proposed Project

Unfortunately, the final determination of required work can only be made after a thorough inspection of the outlet works has been conducted under dry conditions, which will require

dewatering the reservoir and constructing a cofferdam. It has not yet been possible to do this. Thus, the new engineer, based upon the .inspections that he has been able to make, has addressed a range of possible corrective measures, from a temporary "fix" to an all inclusive permanent "fix" which would replace all of the gates (6) and their operating mechanisms.

It has been concluded that it would not be prudent or safe to operate on a long-term basis with only minor, temporary

repairs. Of the remaining alternatives, the District's new engineer is of the opinion that, at a minimum, three of the six

(5)

gates and their operating mechanisms must be replaced at an

estimated cost of $700,000. This work would be done in the

winter of 1986-87, at which time the reservoir would also be dewatered and a final determination as to the needed corrective

measures made. Appropriate claims, if any, against the first

engineer and/or the contractor will be further evaluated at that time also.

Proposed Financing

The financing proposed for this additional work is to

provide funds, part grant and part loan in the same proportions.

as for the original project, as follows:

CWCB grant

CWCB loan (to be repaid by water users) Total

$382,200 317,800 $700,000

Under this financing arrangement, the District would have to pay the CWCB $18,521.38 per year for 40 years for a total repayment

of $740,855.36. This loan would be in addition to the original

$515,000 loan to the District.

Recommendation

The Board recommends that the General Assembly amend the authorization for the subject project to provide increased

funding of $70~1000 per the terms of the proposed financing set

(6)

-4-out above and subject to the conditions that:

(1) The District must demonstrate to the Board's

satisfacion its ability to pay both loans before the Board can make the second loan,

(2) The District must pursue to the Board's satisfaction

any claims for recovery which it may have against the District's first engineer, the contractor, the issuers of surety bonds, or other third parties,

(3) Any funds recovered by the District in the event

liability is fixed on a third party for failure to properly perform the initial work shall, less the District's expenses to prosecute any sucn claims, be immediately paid over by the

District to the Board with 45.4 percent of any such funds being

credited toward the repayment of the District's second loan, and

(4) The State Engineer must certify to the Board that the

previously agreed to operating agreement for the state's use of the reservoir for compact purposes under the Rio Grande Compact has been re-affirmed by the District to his staisfaction before the Board can expend any further money on the project.

References

Related documents

The data collected and subsequent analysis resulted in a database that contained the following information for each seepage measurement location: maximum change in water

46 Konkreta exempel skulle kunna vara främjandeinsatser för affärsänglar/affärsängelnätverk, skapa arenor där aktörer från utbuds- och efterfrågesidan kan mötas eller

Exakt hur dessa verksamheter har uppstått studeras inte i detalj, men nyetableringar kan exempelvis vara ett resultat av avknoppningar från större företag inklusive

The increasing availability of data and attention to services has increased the understanding of the contribution of services to innovation and productivity in

Av tabellen framgår att det behövs utförlig information om de projekt som genomförs vid instituten. Då Tillväxtanalys ska föreslå en metod som kan visa hur institutens verksamhet

Närmare 90 procent av de statliga medlen (intäkter och utgifter) för näringslivets klimatomställning går till generella styrmedel, det vill säga styrmedel som påverkar

Den förbättrade tillgängligheten berör framför allt boende i områden med en mycket hög eller hög tillgänglighet till tätorter, men även antalet personer med längre än

The EU exports of waste abroad have negative environmental and public health consequences in the countries of destination, while resources for the circular economy.. domestically