• No results found

Abstract Impact of Wind Farm Control Technologies on Wind Turbine Reliability

N/A
N/A
Protected

Academic year: 2021

Share "Abstract Impact of Wind Farm Control Technologies on Wind Turbine Reliability"

Copied!
56
0
0

Loading.... (view fulltext now)

Full text

(1)
(2)

Teknisk- naturvetenskaplig fakultet UTH-enheten Besöksadress: Ångströmlaboratoriet Lägerhyddsvägen 1 Hus 4, Plan 0 Postadress: Box 536 751 21 Uppsala Telefon: 018 – 471 30 03 Telefax: 018 – 471 30 00 Hemsida: http://www.teknat.uu.se/student

Abstract

Impact of Wind Farm Control Technologies on Wind

Turbine Reliability

Julia Walgern

Cost efficient operation and maintenance strategies are crucial for reducing cost of wind energy. Since the regime change from feed-in tariffs to an auction-based bidding system for capacity in most European wind projects, levelized cost of energy is challenged constantly. Therefore, new technologies such as new controllers are developed to improve operation and to increase profit. Previous research studies demonstrated the advantage of increased power output of wake redirection control. However, understanding and quantifying the impact of wind farm control technologies on operation and maintenance strategies is inevitable to evaluate the economic feasibility of such new technologies. Thus, an event-based O&M simulation tool has been developed. Besides general modules, such as the wind turbine model, the weather forecasting model and a model for simulating corrective and planned maintenance, the developed tool also takes wake effects into account. This allows considering different power productions for each individual turbine and a failure rate distribution within the wind farm which is based on altering loads on the different components. Both aspects are driven by changes in operation when applying a new controller technology. Exemplarily, the economic feasibility of a closed-loop active wake steering control has been analysed. Main achievements of this study are the possibility to quantify the impact of the active wake steering control on O&M related KPIs. Results show that additional loads caused by applying yaw-misalignment and redirecting wake, lead to an increase in OPEX. However, the achieved energy production gain and thus related additional revenue exceeds additional cost in the case study. Nonetheless, the study reveals that the profitability of the controller is highly dependent on the electricity price which can be acquired during the wind farm’s lifetime.

MSc ET 19002

(3)
(4)

ACKNOWLEDGEMENTS

(5)

TABLE OF CONTENTS

ABSTRACT ... i

ACKNOWLEDGEMENTS ... ii

LIST OF FIGURES ... iiv

LIST OF TABLES ... v

LIST OF ABBREVIATIONS ... vi

LIST OF SYMBOLS ... viii

1 INTRODUCTION ... 1

2 LITERATURE REVIEW ... 2

2.1 Introduction to Maintenance ... 2

2.1.1 Maintenance Classification... 2

2.1.2 Offshore Maintenance ... 3

2.2 Maintenance Optimization for Wind Turbines ... 3

2.3 Controller Technologies ... 4

2.3.1 Closed-loop Control ... 5

2.3.2 Wake Effects and their Impact on Operation ... 6

3 METHODOLOGY ... 8

3.1 Wind Turbine Model... 8

3.1.1 Yield Model ... 9

3.1.2 Component Model ... 10

3.1.3 Reliability Modelling ... 11

3.2 Reference Wind Farm ... 14

3.3 Weather Forecast Model ... 15

3.4 Maintenance Scenarios ... 16

3.4.1 Planned Maintenance ... 17

3.4.2 Corrective Maintenance ... 17

3.5 Service Team, Vessels and Spare Parts ... 20

3.6 Economic Evaluation ... 21

3.7 Controller Technology Implementation ... 22

3.7.1 Updated Yield Model ... 22

3.7.2 Updated Failure Rate Model... 25

3.8 Simulation Setup ... 31

4 RESULTS AND DISCUSSION ... 33

4.1 Tool comparison and validation ... 33

4.2 Impact on energy calculation considering wake effects ... 34

4.3 Non-controller case vs. yaw-controller case ... 34

4.4 Impact on Maintenance Strategies ... 35

4.5 How robust are these results? ... 37

5 CONCLUSION AND OUTLOOK ... 39

(6)

LIST OF FIGURES

Figure 1: Maintenance Classification (based on DIN EN 13306). ... 2

Figure 2: Techniques considered for redirecting wake (Fleming et al., 2014) ... 5

Figure 3: The concept of closed-loop wake redirection (Raach et al., 2017). ... 6

Figure 4: DTU 10 MW Reference Wind Turbine Power Curve (Bak et al., 2013) ... 9

Figure 5: Normalised annual failure rates of the DTU 10 MW RWT (Hendriks, 2015) ... 11

Figure 6: The Bathtub Curve (Reder, 2018)... 12

Figure 7: NORCOWE RWF layout (CL-Windcon D1.1, 2017). ... 14

Figure 8: FINO3 wind rose (CL-Windcon D1.1, 2017). ... 15

Figure 9: Flowchart corrective maintenance implemented in openO&M ... 19

Figure 10: Power scaling factor visualisation based on wake simulation without controller implementation ... 24

Figure 11: Power scaling factor visualisation based on wake simulation with controller implementation ... 24

Figure 12: Turbine layout (Tchakoua et al., 2014) ... 25

Figure 13: Reference systems (Germanischer Lloyd, 2010) ... 28

Figure 14: Change in DEL [in %] of blade root edgewise moment (RootMxb) and blade root flapwise moment (RootMyb) in comparison to the average DEL of the WF for the non-controller case ... 29

Figure 15: Change in DEL [in %] of blade root edgewise moment (RootMxb) and blade root flapwise moment (RootMyb) for the yaw-controller case in comparison to the DELs of the non-controller case ... 29

Figure 16: Change in DEL [in %] of the non-rotating shaft bending moments at the tip of the low-speed shaft in comparison to the average DEL of the WF for the non-controller case ... 30

Figure 17: Change in DEL [in %] of the non-rotating shaft bending moments at the tip of the low-speed shaft for the yaw-controller case in comparison to the non-controller DELs ... 30

Figure 18: Convergence behaviour of the simulation tool with increasing number of iterations for Monte-Carlo simulation ... 32

Figure 19: Energy generation by each wind turbine in its whole life time ... 34

(7)

LIST OF TABLES

Table 1: DTU 10 MW Reference Wind Turbine Main Characteristics (Bak et al., 2013) ... 8

Table 2: Annual failure rates of DTU 10 MW RWT (Hendriks, 2015). ... 14

Table 3: Input planned maintenance (Bak et al., 2017) ... 20

Table 4: Input repair times unplanned maintenance [hrs] (based on Carroll et al., 2015) ... 20

Table 5: Required vessel type and number of required technicians for unplanned maintenance (Carroll et al., 2015) ... 20

Table 6: Vessel information (Bak et al., 2017) ... 21

Table 7: Material cost [€] (Carroll et al., 2015) ... 22

Table 8: Vessel cost (Bak et al., 2017) ... 22

Table 9: List of sensors (CL-Windcon D4.1, 2019) ... 27

Table 10: Failure rate scaling factors ... 31

Table 11: Simulation overview ... 31

Table 12: Results tool comparison ... 33

(8)

LIST OF ABBREVIATIONS

AEP Annual Energy Production APC Active Power Control AWC Active Wake Control BOP Balance of Plant

CDF Cumulative Density Function CMS Condition Monitoring System CTV Crew Transfer Vessel

DEL Damage Equivalent Load

DOWEC Dutch Offshore Wind Energy Converter DTU Technical University of Denmark

ECN Energy research Center of the Netherlands

FINO Forschungsplattformen in Nord und Ostsee (Research Platforms in North and Baltic Sea)

FLORIS FLOw Redirection and Induction in Steady-state IPC Individual Pitch Control

JUV Jack-up vessel

KPI Key Performance Indicator LCOE Levelized cost of energy LES Large Eddy Simulation MTTF Mean Time to Failure

NORCOWE Norwegian Centre for Offshore Wind Energy NOWIcob Norwegian Offshore Wind cost and benefit NPV Net-present value

O&M Operation and Maintenance OPEX Operational expenditure OMCE Operation and Cost Estimator OOP Out-of-plane

OWECOP Offshore Wind Energy Cost and Potential OWF Offshore Wind Farm

PDF Probability Density Function PoF Probability of Failure RWF Reference Wind Farm RWT Reference Wind Turbine

(9)
(10)

LIST OF SYMBOLS

𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦 Time-based availability [%] 𝛼 Power law exponent [-]

𝛽 Shape parameter of Weibull distribution [-] 𝐶𝐹(𝑡) Cash flow in period 𝑡 [€]

𝐷𝑜𝑤𝑛𝑡𝑖𝑚𝑒𝑤𝑓 Cumulative downtime of all wind turbines in the wind farm [hrs]

ΔLSSTipMys Change in DEL of the non-rotating shaft bending moment at the tip of the low-speed shaft [%]

ΔLSSTipMzs Change in DEL of the non-rotating shaft bending moment at the tip of the low-speed shaft [%]

Δ𝑅𝑜𝑜𝑡𝑀𝑥𝑏 Change in DEL of the blade root edgewise moment [%] Δ𝑅𝑜𝑜𝑡𝑀𝑦𝑏 Change in DEL of the blade root flapwise moment [%]

𝐸 Energy [kWh]

𝐸(𝑃𝑡𝑢𝑟𝑏𝑖𝑛𝑒) Expected value for the power production of a specific turbine

[kWh]

𝐸𝑡𝑜𝑡 Cumulative energy production of the entire wind farm [MWh]

𝑓(𝑡) Probability density function [-] 𝐹(𝑡) Cumulative density function [-]

Γ Gamma function [-] 𝑖 Discount rate [%] 𝑘𝑝𝑜𝑤𝑒𝑟 Power scaling factor [-]

𝐿𝑖𝑓𝑒𝑡𝑖𝑚𝑒𝑤𝑓 Cumulative lifetime of all wind turbines in the wind farm [hrs]

𝜆 Exponential failure rate [1/year]

𝜆𝑎𝑐𝑡𝑢𝑎𝑙 Actual/adjusted exponential failure rate [1/year]

𝜆𝑏𝑎𝑠𝑒 Base exponential failure rate [1/year]

𝜆𝑖 Exponential failure rate for subsystem 𝑖 [1/year]

𝜆𝑖,𝑚𝑎𝑗𝑜𝑟 Exponential failure rate for subsystem 𝑖 and a respective major

failure [1/year]

𝜆𝑖,𝑚𝑖𝑛𝑜𝑟 Exponential failure rate for subsystem 𝑖 and a respective minor

failure [1/year]

𝜆𝑖,𝑚𝑜𝑑𝑒 Exponential failure rate for subsystem 𝑖 with a particular failure

mode [1/year]

𝜆𝑖,𝑟𝑒𝑝𝑙𝑎𝑐𝑒𝑚𝑒𝑛𝑡 Exponential failure rate for subsystem 𝑖 and a respective

replacement [1/year] 𝑀𝑇𝑇𝐹 Mean time to failure [hrs]

(11)

𝑁𝑃𝑉 Net-present value [€]

𝑁𝑖 Total number of times wave height state 𝑖 appears [-]

𝑛𝑖𝑗 Number of transitions from wave height state 𝑖 to wave height state

𝑗 [-]

𝑛𝑖𝑘 Number of times wind speed 𝑘 occurs when wave height state 𝑖 is

present [-]

𝑛𝑖𝑙 Number of times wind direction 𝑙 occurs when wave height state 𝑖

is present [-]

𝜂 Scale parameter of Weibull distribution [-] 𝑃 Power [kW]

𝑃𝑡𝑢𝑟𝑏𝑖𝑛𝑒(𝑢, 𝑑) Power output for a specific turbine, a specific wind speed 𝑢 and a

specific wind direction 𝑑 [kW] 𝑝𝑒𝑙 Electricity price [€/MWh]

𝑃(𝑤𝑎𝑣𝑒 ℎ𝑒𝑖𝑔ℎ𝑡)𝑚 Probability matrix for wave height occurrences for month 𝑚 [%]

𝑃′(𝑤𝑖𝑛𝑑 𝑠𝑝𝑒𝑒𝑑)𝑚 Probability matrix for wind speed occurrences for month 𝑚 [%] 𝑃′′(𝑤𝑖𝑛𝑑 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛)

𝑚 Probability matrix for wind direction occurrences for month 𝑚 [%]

𝑝𝑖𝑗 Probability that wave height state 𝑖 is followed by wave height state

𝑗 [%] 𝑝′

𝑖𝑘 Probability that wind speed 𝑘 occurs when wave height state 𝑖 is

present [%]

𝑝′′𝑖𝑙 Probability that wind direction 𝑙 occurs when wave height state 𝑖 is present [%]

PoF𝑖,𝑚𝑜𝑑𝑒 Probability of failure of subsystem 𝑖 with a particular failure

mode [%]

𝑝(𝑢 = 𝑥 ∩ 𝑑 = 𝑦) Joint probability of occurrence of a specific wind speed 𝑢 and wind direction 𝑑 [%]

𝜋𝑖 Failure rate scaling factor of component 𝑖 [-]

𝑅𝑒𝑣𝑒𝑛𝑢𝑒 Cumulative revenue of all turbines in the wind farm [€] 𝑡 Time [hrs]

𝜏 Torque [Nm]

𝑈𝑐𝑢𝑡 𝑖𝑛 Cut-in wind speed [m/s]

𝑈𝑐𝑢𝑡 𝑜𝑢𝑡 Cut-out wind speed [m/s]

𝑈ℎ𝑢𝑏 ℎ𝑒𝑖𝑔ℎ𝑡 Wind speed at hub height [m/s]

𝑈𝑟𝑒𝑓𝑒𝑟𝑒𝑛𝑐𝑒 Wind speed at reference height [m/s]

(12)

1 INTRODUCTION

The European Commission set a target of at least 32% renewable energy production in the EU by 2030 (Renewables energy directive (2018/2001)). In order to reach this goal, WindEurope (2017) predicts different scenarios for wind energy capacity installations and the most conservative case forecasts an installed capacity of 256 GW. Divided into 207 GW onshore and 49 GW offshore installations, wind energy would generate 21.6% of the EU’s power demand in 2030 (WindEurope, 2017). With increasing numbers of installed wind farms, available space for possible installation sites gets smaller. Moreover, there is an increasing trend of wind farms with bigger capacities. Therefore, the probability of allocating turbines closely enough to each other that they influence the performance of neighbouring turbines increases. This influence is known as wake effects. Each wind turbine extracts energy from the air stream which results in reduced wind speed and increased turbulence intensity for the respective turbines downstream. For wind farms with many turbines installed such as Horns Rev, the power loss due to wake effects of some wind turbines has been estimated to up to 25% (Barthelmie et al., 2010).

In order to increase wind farms’ production, and therefore revenue, the approach from optimising each turbine individually (“greedy” control) has shifted to optimising the power generation of the wind farm as a whole. Minimising wake effects by redirecting wake is studied in detail (see Jiménez et al., 2010; Fleming et al., 2016; Gebraad et al., 2014). Advantages regarding increased power output of wake redirection control has been shown in several studies by performing high-fidelity simulations (Gebraad et al., 2014), wind tunnel tests (Campagnolo et al., 2016, Bastankhah and Porté-Agel, 2016), and full-scale field experiments (Fleming et al., 2017). However, all aforementioned studies are based on open-loop control. Doekemeijer et al. (2018) analysed the additional benefit of the closed-loop control approach in comparison to “greedy” and open-loop control and identified an additional power increase of around 4% to 8 % to the latter one.

However, applying wake-redirecting controller technologies can have an impact on the availability of the wind farm as additional equipment is installed at the turbines which affects the way how the turbines are operated. Additionally, load distributions on the turbines’ components can change. Consequently, the failure behaviour of the turbines could change which leads to different maintenance actions in comparison to a wind farm without controller technologies installed.

The goal of this study is to evaluate the economic feasibility of such controller technologies. As controller technology the widely studied yaw-misalignment concept has been chosen as an example to compare maintenance scenarios without and with such a controller installed. In order to quantify the impact of the controller, an O&M tool has been developed and simulations have been run which have been analysed and evaluated afterwards.

(13)

2 LITERATURE REVIEW

2.1 Introduction to Maintenance

Maintenance is defined as “the process of keeping something in good condition” (Oxford Dictionary, 2019). In former times, solely corrective maintenance was carried out after a failure occurred due to missing knowledge about the components of the machine. In order to minimise downtimes preventive maintenance was introduced. With gaining better insights of technology and collecting operation data, finally predictive maintenance was developed. An overview of maintenance classifications is presented in subchapter 2.1.1. Afterwards, the practice of offshore maintenance is described in subchapter 2.1.2.

2.1.1 Maintenance Classification

The European Standard defines maintenance as the “combination of all technical, administrative and managerial actions during the life cycle of an item intended to retain it in, or restore it to, a state in which it can perform the required function” (DIN EN 13306). Maintenance tasks comprise on the one hand the organisation and planning based on observation and analyses, such as regular inspection, condition monitoring, functionality tests, fault diagnosis, and fault localisation. On the other hand, the planned maintenance tasks need to be carried out in form of routine maintenance, overhaul, restoration, repair, temporary repair, improvement, modification, rebuilding, modernisation, and exceptional maintenance (Walgern et al, 2017).

Maintenance can be distinguished in scheduled and unscheduled maintenance. Different maintenance strategies can be derived as shown in Figure 1.

Figure 1: Maintenance Classification (based on DIN EN 13306).

(14)

2.1.2 Offshore Maintenance

During the operational phase of a project, the trade-off between lost revenue and increasing cost for performing maintenance is the primary driver for an offshore wind farm (OWF) project owner to decide on a maintenance strategy. Lost revenues can be derived from the availability of the wind farm which is calculated from downtimes. Downtime depends on both, the actual time spent on repairing components and the waiting time before the mission can start. The latter differs significantly for onshore and offshore maintenance (Sørum et al., 2018). For OWFs both, the time for preparation and allocating staff and spare parts to the farm as well as the waiting time for suitable weather windows can be significantly higher. Therefore, a thorough O&M strategy is needed which includes O&M facilities and ports, vessels and equipment, maintenance strategies and schedules, replacement of main components, parts and consumables such as oil, grease, filters, monitoring and surveying of turbine blades, foundations, scour protection, and cables. Performing maintenance offshore is subject of several constraints: First, depending on the failure and the component, lead times of spare parts can be quite high. Especially bigger components require well planned logistics. Second, different vessel types are utilised for varying tasks. Crew transfer vessels (CTVs) are available for daily operation and are used for the transportation of technicians, tools, and small components. In case an OWF is further away from shore and the response time of a failure is critical, a helicopter can substitute the CTV in order to transfer technicians faster. A jack-up vessel (JUV) is required if heavy components have to be exchanged. Diving support vessels are used to perform underwater inspections and cable laying vessels are utilized in case a power cable is damaged and needs to be replaced. Also, an accommodation vessel can be considered if there are long distances between shore and the OWF. It minimises the access time to the turbines as travel times of technicians are reduced. While CTVs are usually permanently leased on a fixed contract, the other types of vessels are chartered in the spot market if needed (Ioannou et al., 2018). Third, technicians need to be available. Typically, offshore personnel work on a shift based on two weeks working offshore followed by two weeks having off. The shift length is normally 12 working hours per day while a break of one hour is foreseen according to the European working time regulations for offshore workers (Offshore Working Time Ordinance, 2013). Fourth, offshore operations are dependent on weather conditions. All aforementioned vessel types are subject to weather limits specified by maximum significant wave heights and wind speeds. Only if the sea state is safe, maintenance can be carried out.

At least two maintenance strategies are applied to each OWF: Scheduled maintenance is carried out once a year in order to prevent breakdowns due to missing maintenance. Typically, these tasks are scheduled for summer to guarantee suitable weather windows. Corrective maintenance is performed in case of a failure. It can be related to long downtimes depending on the type of failure and the time of the year the failure occurs as all constraints mentioned above need to be considered. In order to minimise corrective maintenance tasks and its related downtimes, OWF operators monitor the turbines and try to derive predictive maintenance strategies by analysing the collected data. Therefore, SCADA systems are installed in nearly all operating wind turbines nowadays. Additionally, condition monitoring systems (CMS) can facilitate a thorough analysis of the state of several components of the turbine. However, the installation of CMS is quite expensive, and the economic feasibility depends on the trade-off between early failure detection and initial investment cost (Reder, 2018).

2.2 Maintenance Optimization for Wind Turbines

(15)

in order to assess different aspects of O&M or O&M as a whole. Qualitative models are not considered further in this report as they do not allow for quantifying the impact of the controller. Hoffmann (2011) provides a thorough overview of existing simulation models. 49 different models are presented. He highlights the Dutch Offshore Wind Energy converter (DOWEC) and the Offshore Wind Energy cost and Potential (OWECOP) model. These models were developed by the Energy Research Center of the Netherlands (ECN) which also developed the Operation and Cost Estimator (OMCE) model. Next to the recent ECN O&M tool (OMCE) (Rademakers et al., 2009), the NOWIcob tool presented by Hofmann and Sperstad (2013) is a commonly used O&M model. Dinwoodie et al. (2015) provide a verification process for O&M simulation models and as an example it has been applied to four O&M models comprising NOWIcob, University of Stavanger offshore wind simulation model, ECUME model and Strathclyde University Centre for Doctoral Training offshore wind OPEX model.

Bendlin et al. (2018) categorise several O&M tools in regards of the function considering failure, weather, routing, scheduling and economic modules. Monte-Carlo methods, Weibull distributions, Markov Chains and Poisson Processes have been identified as commonly used approaches. It has been pointed out that only a minority of present tools combine probabilistic theories with the expert knowledge of O&M professionals.

2.3 Controller Technologies

As wind farms comprise several turbines and with time especially the size of OWFs increased but space is limited, the distance between turbines is small enough that wake effects occur. Wake streams of upwind turbines affect downwind turbines in two ways. On the one hand, the wind speed downwind is reduced. On the other hand, the turbulence intensity increases as the air flow is mixed when extracting energy. Consequently, the downwind turbines generate less energy and face higher structural loads. Especially, if the rotor is only partially affected due to partial wake overlaps, the turbine experiences inhomogeneous inflow conditions which result in even higher structural loads (Andueza et al., 2018).

In order to maximise the overall power production and / or to minimise fatigue loading of the turbines, turbine technology has overcome passively controlled fixed-speed stall-regulated machines and moved to actively controlled variable-speed pitch regulated ones. Wind farm control comprises both, the concept of down-regulation and wake redirection control or wake steering. Down-regulation can be realised by either blade pitch or generator torque usage implementing active power control (APC) or active wake control (AWC) which is also known as axial induction control, whereas wake redirection control is based on misaligning the rotor of the upstream turbine. For achieving the redirection either yaw motors or individual pitch control (IPC) is used to create a yaw-moment (Astráin et al., 2017).

(16)

Figure 2: Techniques considered for redirecting wake (Fleming et al., 2014)

It can be distinguished between yaw induced or tilt induced techniques. The arrows show which component angles are adjusted. However, in recent turbines there is no possibility of modifying tilt angles yet but is mentioned for completeness (Fleming et al., 2014).

2.3.1 Closed-loop Control

So far, mainly open-loop wake steering has been used. It is a method to redirect the wake by either yawing the wind turbine or by cyclic blade pitching in order to avoid wake overlaps. Many studies evaluated the concept of open-loop control and advantages have been found in comparison to applying the common practice “greedy” control approach in which each turbine is optimised on its own without considering the other turbines within the wind farm.

Fleming et al. (2014) compared different methods for redirecting turbine wakes. The availability to do so and the effects on turbine power capture and structural loads have been investigated using the high-fidelity wind farm simulation tool SOWFA. Yaw misalignment was found to provide sufficient wake redirection with additional load reduction on components, while needed improvement for IPC control was suggested as it has shown considerable increases in blade loading.

Gebraad et al. (2014) used the FLORIS model to predict steady-state wake locations, the effective flow velocities at each turbine, and the resulting turbine electrical energy production in respect to axial induction and yaw angle for a case which comprises six turbines. It has been demonstrated that the control method applied increases the energy generation of the wind farm with reducing the loads of the turbines at the same time. It has been shown that the power loss of upstream turbines due to yaw-misalignment is compensated by a larger power gain in downstream turbines. However, it is pointed out that found benefits will be smaller in real wind farms as the distances between the turbines are greater than in the case study.

Jiménez et al. (2010) also studied the consequences of yaw misalignment and simulated the turbulences for different yaw angles using a large eddy simulation (LES) model. It has been demonstrated that yaw angles greater than 30° are unfeasible for yaw-misalignment which is in line with the observations of experimental tests (see Parkin et al., 2001).

(17)

influence the final wake position and consequently the reached performance. (Andueza et al., 2018)

As a consequence, closed-loop approaches have been developed to overcome above mentioned disadvantages. A lidar-based closed-loop wake redirection was first introduced by Raach et al. (2016, 2017) to account for temporal disturbances. They presented a controller for closed-loop wake redirection which uses wake tracking information to define the new angle of the turbine’s yaw actuator for steering the wake stream into a desired direction. The controller is based on two main tasks: the estimation task and the control task. An overview of the controller can be seen in Figure 3.

Figure 3: The concept of closed-loop wake redirection (Raach et al., 2017).

While the estimation task provides an estimation of the wake position to the control task by utilising lidar measurements, the control task compares the received information with the required and defined position and commands a yaw angle to the turbine minimising the error between estimation position and demanded one (Raach et al., 2017). Later, the ability to adapt to temporal changing crosswind disturbances which allows for an increase in the power output in comparison to open-loop approaches has been demonstrated in a LES simulation model (Raach et al., 2018). Doekemeijer et al. (2018) compared “greedy” control with open-loop and closed-loop control approaches and quantified the benefits for a case study of nine turbines. The open-loop method can be accounted for an increase of power of around 3%, whereas the closed-loop approach can be accounted for an increase of 7% to 11% in comparison to the “greedy” wind farm operation. Fleming et al. (2017) demonstrated that the concept of wake redirecting using yaw-misalignment works in real setups by conducting a field test at a commercial offshore wind farm in China. For this study the installed yaw controllers have been modified to allow for wake steering according to a yaw control strategy which has been developed using SOWFA and FLORIS.

2.3.2 Wake Effects and their Impact on Operation

(18)

(DEL) for each of the mentioned load signals. It has been noticed that the upstream turbine faces an increase or decrease in the blade OOP bending depending on the chosen angle. It has been proposed to limit yaw misalignment only to positive yaw angles which results in mostly positive lifetime expectations. Moreover, yaw-misalignment leads normally to a reduction in power which results in smaller loads for drivetrain, tower and yaw mechanism. Furthermore, introducing individual pitch control could mitigate additional loading due to partial wake overlap. In contrast, the downstream turbine experiences an increase in all loads which is explained by moving from full to partial wake overlap which is based on the assumptions made for the base case having full wake overlap. Therefore, Fleming et al. (2016) analysed wind farm optimisation considering both, yaw control and farm layout – first independently and afterwards combined which can have a beneficial effect.

(19)

3 METHODOLOGY

In order to analyse and especially quantify the impact of controller technologies on wind farm availability, different O&M scenarios of an offshore wind farm need to be simulated. Several commercial O&M simulation tools are available for this (e.g. Shoreline). However, only pre-set strategies can be simulated and no adjustments in the code can be made. Therefore, commercial tools provide not enough flexibility to analyse new technology approaches. Consequently, an own model has been developed which can take both maintenance scenarios into account, turbines without yaw misalignment controller and turbines with yaw misalignment controller. Considering different wind farm specific inputs, a MATLAB® based simulation tool calculates the availability, cost and revenue of the wind farm over its lifetime.

In the following chapters the model and its input data are described more in detail. Subchapter 3.1 gives an overview of the wind turbine model. This comprises the yield model of the wind turbine, the component model and the aspect of reliability modelling. Subchapter 3.2 presents the reference wind farm used. Subchapter 3.3 describes the weather forecast model. How the maintenance campaigns are organised and implemented is specified in 3.4. It is differentiated between planned and unplanned maintenance. In 3.5 the required input data for service teams, vessels and spare parts are presented. Subchapter 3.6 deals with the economic evaluation of the maintenance scenarios. In subchapter 3.7 the implementation of the yaw-misalignment controller is explained. Last, in 3.8 the simulation cases for the study are defined.

3.1 Wind Turbine Model

In order to analyse the impact on operation and maintenance of different controller strategies which results in varying availability and costs, it is important to simulate the wind turbines in the wind farm as accurately as possible. As the size of turbines increased steadily the last years, the DTU 10 MW reference wind turbine has been utilised in order to apply a realistic turbine size. Main characteristics of the reference wind turbine are shown in Table 1.

Table 1: DTU 10 MW Reference Wind Turbine Main Characteristics (Bak et al., 2013)

Description Value Rated Power [MW] 10 Rotor diameter [m] 178.3 Hub height [m] 119 Cut-in speed [m/s] 4 Rated speed [m/s] 11.4 Cut-out speed [m/s] 25 Cut-in rotor speed [RPM] 6 Rated rotor speed [RPM] 9,6

(20)

3.1.1 Yield Model

A wind turbine yield model is used for the calculation of the generated energy of the entire wind farm. First, the generated energy of each turbine is determined based on the weather forecast model (see chapter 3.3) and the turbine’s power curve. Second, the generation of all turbines is summed up to obtain the wind farm’s total energy production.

The DTU 10 MW reference wind turbine is chosen to simulate a typical turbine size. The power curve can be seen in Figure 4. It is characterised by a cut-in wind speed of 4 m/s, a rated wind speed of 11.4 m/s, and a cut-out wind speed of 25 m/s.

Figure 4: DTU 10 MW Reference Wind Turbine Power Curve (Bak et al., 2013)

In order to utilise the power curve, the wind speed at hub height is required. Wind data measured by a met mast is providing wind speeds at a reference height. This measured data needs to be extrapolated to the wind speed at hub height which can then be applied to the power curve. Therefore, the power law is utilised:

𝑈ℎ𝑢𝑏 ℎ𝑒𝑖𝑔ℎ𝑡= 𝑈𝑟𝑒𝑓𝑒𝑟𝑒𝑛𝑐𝑒∙ (

ℎ𝑢𝑏 ℎ𝑒𝑖𝑔ℎ𝑡 𝑟𝑒𝑓𝑒𝑟𝑒𝑛𝑐𝑒 ℎ𝑒𝑖𝑔ℎ𝑡)

𝛼

(3-1)

where 𝑈𝑟𝑒𝑓𝑒𝑟𝑒𝑛𝑐𝑒 is the wind speed at reference height in 𝑚/𝑠 measured at the met mast.

𝐻𝑢𝑏 ℎ𝑒𝑖𝑔ℎ𝑡 and 𝑟𝑒𝑓𝑒𝑟𝑒𝑛𝑐𝑒 ℎ𝑒𝑖𝑔ℎ𝑡 are used in 𝑚𝑒𝑡𝑒𝑟𝑠 which is especially important for equation (3-2). The power law exponent 𝛼, which has no unit, is given by Justus et al. (1978):

𝛼 = 0.37 − 0.088 ∙ ln(𝑈𝑟𝑒𝑓𝑒𝑟𝑒𝑛𝑐𝑒) 1 − 0.088 ∙ ln (𝑟𝑒𝑓𝑒𝑟𝑒𝑛𝑐𝑒 ℎ𝑒𝑖𝑔ℎ𝑡10 )

(3-2)

Utilising wind speed data at a reference height of 10 meters, simplifies equation (3-2) to: 𝛼 = 0.37 − 0.088 ∙ ln(𝑈𝑟𝑒𝑓𝑒𝑟𝑒𝑛𝑐𝑒) (3-3)

Afterwards, the power is determined as follows:

(21)

where 𝑈𝑐𝑢𝑡 𝑖𝑛 is the cut-in wind speed and 𝑈𝑐𝑢𝑡 𝑜𝑢𝑡 the cut-out wind speed of the turbine. If the

wind speed is outside the given boundaries 𝑈𝑐𝑢𝑡 𝑖𝑛 and 𝑈𝑐𝑢𝑡 𝑜𝑢𝑡 of the power curve, the wind

turbine is not producing any power. Within the boundaries, the power at hub height is linearly interpolated for 𝑈1≤ 𝑈ℎ𝑢𝑏 ℎ𝑒𝑖𝑔ℎ𝑡≤ 𝑈2 between 𝑃1 and 𝑃2, where 𝑈1 and 𝑈2 are the next smaller

and bigger wind speed values of the power curve, and 𝑃1 and 𝑃2 are the respective power outputs.

Afterwards the energy can be calculated as:

𝐸 = 𝑃 ∙ 𝑡 (3-5) where 𝑡 is the time given in ℎ𝑜𝑢𝑟𝑠.

Calculating the generated energy as mentioned above, underlies the assumption that the yaw controller always yaws into the current wind direction in order to retrieve 100% of the power. Furthermore, travel times of the yaw system when adjusting to a new wind direction are neglected in this approach as these ones have a minor impact considering the total life time of the wind farm.

3.1.2 Component Model

(22)

Figure 5: Normalised annual failure rates of the DTU 10 MW RWT (Hendriks, 2015)

Second, the downtimes caused by each component’s failures are investigated. Based on data of Carroll et al. (2015) who analysed offshore wind turbines of the size between 2 and 4 MW, the main components causing huge downtimes if a replacement is needed, are the hub (298 hours), the blades (288 hours), the gearbox (231 hours), the circuit breaker/relay (150 hours), and the generator (81 hours). Reder (2018) investigated the downtimes of turbines below and above 1 MW rated power. For turbines above 1 MW, the normalised downtimes indicate the gearbox, the generator, the blades and the pitch system as the most critical components. Due to a lack of recent data, many studies analyse the downtimes of onshore turbines as indications for offshore turbines or utilise data of smaller, older offshore turbines. Consequently, data provided by Carroll et al. (2015) is found to be applicable and accurate enough for this study.

Considering the findings above, the component model used in this study comprises seven components: gearbox, generator, pitch system, yaw system, blades, main shaft, and electrical system. Additionally, this component model allows analysing changes in reliability due to applied controller technologies which are driven by the yaw and pitch system.

3.1.3 Reliability Modelling

3.1.3.1 Failure rate distribution types

Reliability modelling is used to simulate the breakdowns of the different components and different failure modes. For each component failure modes are distinguished between minor repairs, major repairs and major replacements. In order to simulate downtimes and uptimes, the concept of mean time to failure (MTTF) is used which describes the expected mean value that a failure occurs:

𝑀𝑇𝑇𝐹 = ∫ 𝑡 ∙ 𝑓(𝑡)𝑑𝑡

∞ 0

(3-6)

(23)

Different failure distributions are known while the Weibull distribution and the exponential distribution are the most common ones used and explained below.

The Weibull distribution’s PDF is given as: 𝑓(𝑡) = 𝛽 𝜂 ( 𝑡 − 𝛾 𝜂 ) 𝛽−1 𝑒−( 𝑡−𝛾 𝜂 ) 𝛽 (3-7)

where 𝑓(𝑡) ≥ 0, 𝑡 ≥ 0 𝑜𝑟 𝛾, 𝛽 > 0, 𝜂 > 0, −∞ < 𝛾 < ∞ with 𝛽 as the shape parameter, 𝜂 as the scale parameter, and 𝛾 as the location parameter. When utilising the Weibull distribution for modelling failure rate distributions, the location parameter is often not used. As a consequence, the three-parameter Weibull distribution is reduced to a two-parameter distribution:

𝑓(𝑡) = 𝛽 𝜂 ( 𝑡 𝜂) 𝛽−1 𝑒−( 𝑡 𝜂) 𝛽 (3-8)

While the scale parameter 𝜂 equals the time in which a defined percentage of failures occur (commonly 63.2%), the shape parameter 𝛽 determines the period of lifetime in which the component is situated. It is distinguished between infant mortality, also called early life, which characterises the early stages of lifetime with a decreasing failure rate (𝛽 < 1), useful life in which a constant failure rate is assumed (𝛽 = 1), and wear-out phase in the end of a component’s lifetime which is described by an increasing failure rate (𝛽 > 1). These different stages and failure types within the lifetime of a component are summarised in Figure 6 which shows the wide known concept of the Bathtub curve.

Figure 6: The Bathtub Curve (Reder, 2018).

For the Weibull distribution the MTTF is given by:

𝑀𝑇𝑇𝐹 = 𝛾 + 𝜂 ∙ Γ (1 𝛽+ 1)

(3-9)

where Γ is the gamma function.

When neglecting the infant mortality and wear-out phase, the distribution simplifies to an exponential distribution. The PDF is defined as:

𝑓(𝑡) = 𝜆 ∙ 𝑒−𝜆𝑡 (3-10)

(24)

𝑀𝑇𝑇𝐹 = 1 𝜆

(3-11)

This simplification makes the exponential distribution the more user friendly one. As failure rate data is scarce and the Weibull parameters are not easy to understand, the exponential distribution is chosen for simulating the MTTF. This decision allows for both, using existing failure rate data bases for the 10 MW DTU reference wind turbine and adjusting failure rates based on expert knowledge if needed more easily.

3.1.3.2 Reliability model

The reliability module simulates the occurrence and severity of the failures for each component of the turbine. Additionally, the time to failure (TTF) for each occurrence is determined which gives the time period until the next failure occurs.

For each component/subsystem of the turbine it is differentiated in three failure modes:

- Minor failure: In case of a minor failure the turbine continues working when the

failure is detected. Only during repair time, the turbine is shut down.

- Major failure: In case of a major failure the turbine is stopped immediately when

the failure occurred. It is out of service until the fault is maintained.

- Replacement: In case of such a severe failure that a replacement is necessary, the

turbine is shut down from the time the failure occurred until the faulty component is exchanged.

Based on the arguments from subchapter 3.1.3.1, the TTF corresponding to each failure mode for a subsystem 𝑖 is modelled by a distribution of an exponential probability density function:

𝑓(𝑡) = 𝜆𝑖,𝑚𝑜𝑑𝑒exp(−𝜆𝑖,𝑚𝑜𝑑𝑒𝑡) (3-12)

where 𝜆𝑖,𝑚𝑜𝑑𝑒is the failure rate for subsystem 𝑖 with a particular failure mode (e.g. minor, major

or replacement). Based on equation (3-12) the cumulative density function (CDF) of the time to failure, which is also the probability of failure (PoF) of the respective subsystem and mode, can be derived:

𝐹(𝑡) = PoF𝑖,𝑚𝑜𝑑𝑒= 1 − exp (−𝜆𝑖,𝑚𝑜𝑑𝑒𝑡) (3-13)

Assuming a serialised system for the failure modes, the failure rate of subsystem 𝑖 can be calculated as follows:

𝜆𝑖= 𝜆𝑖,𝑚𝑖𝑛𝑜𝑟+ 𝜆𝑖,𝑚𝑎𝑗𝑜𝑟+ 𝜆𝑖,𝑟𝑒𝑝𝑙𝑎𝑐𝑒𝑚𝑒𝑛𝑡 (3-14)

Therefore, the probability of failure of subsystem 𝑖 can be calculated as:

𝐹(𝑡) = PoF𝑖 = 1 − exp(−𝜆𝑖𝑡) (3-15)

(25)

3.1.3.3 Failure Rates Base Case

Based on the component model in subchapter 3.1.2, exponential failure rates for the different failure categories (minor failure, major failure and replacement of components) and for each chosen component are applied. The relevant data can be seen in Table 2.

Table 2: Annual failure rates of DTU 10 MW RWT (Hendriks, 2015).

Component Minor failure Major failure Replacement

Gearbox 0.644 0.157 0.028

Generator 0.049 0.018 0.008

Main shaft 0.231 0.026 0.009

Power electrical system 0.370 0.043 0.002

Yaw system 0.259 0.036 0.012

Pitch system 0.397 0.020 0.008

Blades 0.200 0.045 0.040

3.2 Reference Wind Farm

For the simulation, a reference wind farm (RWF) site called NORCOWE is chosen. The RWF has been developed in a Norwegian project called NORCOWE by industry and science partners. The RWF is located around 80 km west of the German island Sylt, and near by the met mast FINO 3 is installed (NORCOWE, 2019). The RWF comprises 80 turbines of the type DTU 10 MW RWT and the layout of the wind farm can be seen in Figure 7. Position 26 and 61 in the layout are the positions of substations. The distance between the rows is 8 rotor diameters and the distance between the turbines is 7 rotor diameters.

(26)

3.3 Weather Forecast Model

According to Bendlin et al. (2018) different approaches are followed simulating weather in recent O&M tools. While Weibull distributions and Markov Chains are the most common ones, also Monte Carlo simulations, weather windows or regression models are used.

As Markov Chains allow for modelling probabilities of future states taking the immediate predecessor into account, this approach is followed and explained hereafter as it is important to have consistent time series in order to check for suitable weather windows in case of necessary maintenance work (see chapter 3.4 below). Discrete Markov Chains are used to simulate the weather conditions including wave height, wind speed and wind direction based on historical data. For the simulation, historical weather data of FINO 3 has been utilised for the Markov Chain model due to the location of the RWF. FINO3 is one of three research platforms supported by the German government allocated in North and Baltic Sea close to permitted offshore wind farms and is collecting among others weather data (FINO3, 2019). The wind rose of FINO3 can be seen in Figure 8.

Figure 8: FINO3 wind rose (CL-Windcon D1.1, 2017).

Historical data of FINO3 comprising wind speed, wind direction, and wave height measured over 10 years between 2000 and 2010 with a resolution of 3 hours has been used.

(27)

where 𝑝𝑖𝑗 is the probability that wave height state 𝑖 is followed by wave height state 𝑗:

𝑝𝑖𝑗 =

𝑛𝑖𝑗

𝑁𝑖

(3-17)

where 𝑛𝑖𝑗 is the number of transitions from wave height state 𝑖 to wave height state 𝑗, and 𝑁𝑖 is

the total number of times wave height state 𝑖 appears.

Additionally, 𝑚 is indicating the month of the year as the probability matrix is determined for each month within the year in order to take care of seasonal changes in the weather pattern. Third, a similar procedure has been applied to obtain the probability matrices for wind speed and wind direction: 𝑃′(𝑤𝑖𝑛𝑑 𝑠𝑝𝑒𝑒𝑑) 𝑚= ( 𝑝′11 ⋯ 𝑝′1𝑛 ⋮ ⋱ ⋮ 𝑝′ 𝑛1 ⋯ 𝑝′𝑛𝑛 ) (3-18) and 𝑃′′(𝑤𝑖𝑛𝑑 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛) 𝑚 = ( 𝑝′′11 ⋯ 𝑝′′1𝑛 ⋮ ⋱ ⋮ 𝑝′′𝑛1 ⋯ 𝑝′′𝑛𝑛 ) (3-19)

Instead of deriving the probabilities of changing from one state into another, the probabilities are defined as the probability that a certain wind speed or wind direction occurs when wave height state 𝑖 is present: 𝑝′𝑖𝑘 = 𝑛𝑖𝑘 𝑁𝑖 𝑎𝑛𝑑 𝑝′′𝑖𝑙 = 𝑛𝑖𝑙 𝑁𝑖 (3-20)

where 𝑛𝑖𝑘 and 𝑛𝑖𝑙 are defined as the number of times wind speed 𝑘 or wind direction 𝑙 occur,

respectively, when wave height state 𝑖 is present.

Fourth, start values which will be applied to the probability matrices are determined. A wave height is chosen randomly considering the probability of occurrence for the starting month. Afterwards, matrices 𝑃′(𝑤𝑖𝑛𝑑 𝑠𝑝𝑒𝑒𝑑) and 𝑃′′(𝑤𝑖𝑛𝑑 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛) are applied to obtain the

respective start values for wind speed and direction.

Fifth, based on the lifetime of the wind farm and the simulation time steps, a weather data series comprising wave height, wind speed and wind direction is determined. This time series can be applied to the power module (see chapter 3.1.1) and is needed to identify suitable weather windows for performing maintenance (compare chapters 3.5 and 3.4).

3.4 Maintenance Scenarios

As described in chapter 2.1.1 it can be distinguished between scheduled and unscheduled maintenance. In the simulation for this is taken care of by implementing planned maintenance and unplanned, also referred as to corrective, maintenance. Both scenarios are explained in detail below.

(28)

3.4.1 Planned Maintenance

Scheduled, also called planned, maintenance is conducted once a year for offshore wind farms (Bak et al., 2017). This is common practice in the industry and the summer months are used for the campaign in order to guarantee most suitable weather conditions. Main tasks performed are inspections, checking and updating consumables such as oil, grease and filters, and small replacements if needed. In order to allow for most suitable weather windows, these tasks are scheduled for summer time.

In the simulation tool, planned maintenance is performed every 12 months to align with common practice of the wind industry. A margin of one month is implemented to allow for a longer weather window and to give some freedom for mission planning. Planned maintenance downtime is defined as the time between the service team arrives at the turbine and finishes the maintenance tasks. Consequently, travel times are not considered in the downtime calculation as the turbine is only stopped when starting the work. However, in case of exceeding one technicians’ shift, the downtime is prolonged by the time of the break in between which can involve travel times back and forth to the onshore base as well.

Moreover, it is assumed that planned maintenance can only take care of minor failures. For bigger failures and needed component replacements which could have arisen during the inspections, another corrective maintenance task needs to be performed. Hence, after the maintenance tasks have been finished, only the mean time to failure variable for minor failures of the respective turbine is updated.

3.4.2 Corrective Maintenance

Corrective maintenance is applied as soon a failure occurs. Depending on the type of failure, the type of component, and the time of the year, it can be related to long downtimes. The O&M tool differentiates between failures which require a JUV and failures which require a CTV. In order to decrease downtimes, respective maintenance campaigns are implemented which do not only repair one turbine but store different maintenance tasks on a campaign list and follow this list during the campaign. While in one JUV campaign all turbines are maintained for which a failure occurred within the lead time of ordering a JUV, a CTV campaign repairs all failures which occurred during night when technicians rest. This difference is due to the usage of vessel type. A JUV is costly and needs to be ordered at the market. This takes time. Instead of just repairing one failure and ordering a JUV for another failure again, all pending turbines which need maintenance are served. Moreover, JUV campaigns are performed in shifts to utilise the JUV to capacity. In comparison, CTV campaigns are only performed during day-shifts as no accommodation is available on this vessel type. All failures which occurred during night are scheduled for the next day-shift. In case not all turbines can be served, the campaign continues the next day.

Both strategies are implemented by checking step by step all constraints. A flow chart of the process can be seen in Figure 9.

After a failure has been detected, first, the respective corrective maintenance campaign needs to be planned and a downtime for mission planning is accounted.

Second, depending on the failure type and its requirements, the mobilisation time is defined. While CTVs are normally owned by the wind farm operator and a fixed number is assigned for each wind farm, JUVs are usually ordered at the supplier market. Therefore, a long lead time can be the consequence (see Table 6).

(29)

Fourth, it is checked if all necessary vessels are available. In case they are not available, either the vessel needs to be acquired at the spot market or it needs to be waited until the vessel finishes the actual mission and is available again. These times are considered as vessel unavailability downtime.

Fifth, the crew availability is checked and in case of waiting for the next available crew due to other ongoing missions, the respective time is tracked as crew unavailability downtime.

Sixth, it is checked if there is a weather window which allows completing the mission considering vessel weather limits. Only if a safe weather state is guaranteed for the whole mission time, the maintenance task is performed. Even though it could be imagined that in reality vessel and crew availability is planned / checked simultaneously considering the weather conditions (e.g. no vessel ordered if weather forecast is unsuitable), the long lead time of a JUV does not allow taking the weather forecast into account. Therefore, it is the wind farm operator’s risk. When thinking about CTV campaigns, vessels are normally available if not still in another mission. As soon the sufficient vessel number returned, the weather forecast is checked for going out again. Therefore, a linear approach checking one constraint after the other for implementation is utilised (see Figure 9).

If all conditions are fulfilled, the mission itself can start and a travel time is considered for transferring vessels, crew and spare parts from the onshore base to the respective turbine. Then, the repair time itself is accounted to the downtime. In case the repair time for one type of failure is longer than one work shift of the crew (which is set to 12 hours), the travel time for going back and forth to the turbine is considered in the downtime calculation as well.

Finally, the turbine is repaired and the next time to failure is determined (see subchapter 3.1.3.2). The total downtime of the turbine can be calculated as the sum of the downtimes accounting for each constraint mentioned above.

In order to plan the next corrective maintenance mission, the travel time back to the shore and a demobilisation time is considered as the next mission can only start after these two steps have been fulfilled as well.

(30)
(31)

3.5 Service Team, Vessels and Spare Parts

In order to simulate the different maintenance campaigns (see subchapter 3.4) a lot of input data is required. The respective numbers for planned and unplanned maintenance as well as vessels and technicians can be found in the tables below. All figures are either based on published literature (Bak et al. (2017) and Carroll et al. (2015)) or experience. Repair times which can be seen in Table 4 are based on Carroll et al. (2015) but are upscaled for the DTU 10 MW RWF to take the bigger turbine size into account.

Table 3: Input planned maintenance (Bak et al., 2017)

Description Value

Annual frequency 1 Required vessel type CTV Number of required technicians 3 Repair time [hrs] 35

Table 4: Input repair times unplanned maintenance [hrs] (based on Carroll et al., 2015)

Component Minor failure Major failure Replacement

Gearbox 16 44 693

Generator 14 48 243

Main shaft 10 36 144

Power electrical system 10 28 54

Yaw system 10 40 147

Pitch system 18 38 75

Blades 18 42 864

Table 5: Required vessel type and number of required technicians for unplanned maintenance (Carroll et al., 2015)

Component Minor failure Major failure Replacement

Gearbox CTV / 2 CTV / 3 JUV / 17

Generator CTV / 2 CTV / 3 JUV / 8

Main shaft CTV / 2 CTV / 3 JUV / 5

Power electrical system CTV / 2 CTV / 3 CTV / 3

Yaw system CTV / 2 CTV / 3 JUV / 5

Pitch system CTV / 2 CTV / 3 JUV / 4

(32)

Table 6: Vessel information (Bak et al., 2017) Vessel type Available number Speed [knots] Technician capacity Mobilisation time [days] Limiting weather criteria CTV 4 20 12 0 Wave: 1.5 [m]

JUV 1 11 100 40 Wind / Wave: 20 [m/s] / 2 [m]

While for CTV campaigns a pool of 12 technicians is available, JUV campaigns are served by external technicians. Maximum 42 technicians are utilised for a JUV campaign as a blade replacement performed in shifts requires at least 42 technicians. All other tasks require less technicians.

3.6 Economic Evaluation

In order to evaluate different maintenance strategies, the O&M tool provides as outputs the availability, generated energy, revenue and costs of the wind farm over its lifetime.

Based on the calculated downtimes introduced in subchapter 3.4 the time-based availability of the wind farm is calculated as follows:

𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦 = 𝐿𝑖𝑓𝑒𝑡𝑖𝑚𝑒𝑤𝑓− 𝐷𝑜𝑤𝑛𝑡𝑖𝑚𝑒𝑤𝑓 𝐿𝑖𝑓𝑒𝑡𝑖𝑚𝑒𝑤𝑓

(3-21)

where 𝐿𝑖𝑓𝑒𝑡𝑖𝑚𝑒𝑤𝑓 is the cumulative lifetime of all wind turbines in the wind farm and 𝐷𝑜𝑤𝑛𝑡𝑖𝑚𝑒𝑤𝑓 is the respective cumulative downtime.

The revenue is calculated based on the cumulative energy production of the entire wind farm (𝐸𝑡𝑜𝑡):

𝑅𝑒𝑣𝑒𝑛𝑢𝑒 = 𝐸𝑡𝑜𝑡∙ 𝑝𝑒𝑙 (3-22)

where 𝑝𝑒𝑙is the electricity price.

Due to a reform of the German Renewable Energies Act (EEG), which entered into force on January 1, 2017 and sets out a regime change from guaranteed feed-in tariffs to an auction-based bidding system for capacity (Walgern et al., 2017), subsidies for produced energy within a wind farm decreased significantly.

As subsidy-free bids have been accepted in first auctions under the reform already (Weston, 2017), only the electricity spot price without an additional market premium will be received. Therefore, for this study a value of 39.18 €/MWh is chosen which represents the averaged EPEX electricity spot price for the years 2011 to 2015.

(33)

Table 7: Material cost [€] (Carroll et al., 2015)

Component Minor failure Major failure Replacement

Gearbox 5000 26670 592500

Generator 1000 14340 236500

Main shaft 1000 14000 232000

Power electrical system 1000 5000 50000

Yaw system 500 3000 12500

Pitch system 500 1900 14000

Blades 5000 43110 445000

For planned maintenance material cost of € 5000 are applied. For all material cost related to unplanned and planned activities, input has been based on Carroll et al. (2015) and expert interviews. The day rate for technicians is € 500. Costs related to the vessels are specified in Table 8.

Table 8: Vessel cost (Bak et al., 2017)

Vessel type Day rate [€] Mobilisation cost [€]

CTV 3200 0

JUV 320000 680000

For both, cost and revenue calculation a net-present value (NPV) approach is chosen as cash flows occur at different times during the wind farm’s life time and need to be discounted to be comparable. The net-present value can be calculated as follows:

𝑁𝑃𝑉 = 𝐶𝐹(𝑡)

(1 + 𝑖)𝑡 (3-23)

where 𝐶𝐹(𝑡) is the cash flow in period 𝑡 and 𝑖 is the discount rate which has been assumed as 5%.

3.7 Controller Technology Implementation

In order to simulate the active wake steering control which is inducing yaw misalignment based on a closed-loop strategy, and therefore also called yaw-controller, additional modules have been implemented in the O&M simulation tool. Conventional O&M simulation tools only allow for the same input for all turbines. Failure rates are assumed to be the same for all turbines within the wind farm and wake affects are not considered. However, to analyse the impact of the controller on the wind farm’s key performance indicators these aspects are important to consider. Therefore, individual inputs and separate simulation of each turbine has been introduced. In the following sub-chapters, the updated yield model considering wake effects and the updated failure rate model is described more in detail.

3.7.1 Updated Yield Model

(34)

which takes wake effects and yaw-misalignment into account. Thus, the energy calculation in equation (3-5) is adjusted to

𝐸 = 𝑃 ∙ 𝑘𝑝𝑜𝑤𝑒𝑟∙ 𝑡 (3-24)

where 𝑘𝑝𝑜𝑤𝑒𝑟 is the power scaling factor.

The Energy Research Centre of the Netherlands (ECN) performed wake simulations applying the controller and obtained the optimal yaw-misalignment for each turbine within the NORCOWE reference wind farm dependent on wind speed and direction. First, the yaw-misalignment settings have been optimised with the ECN FarmFlow model. Afterwards, an analysis of the annual energy production (AEP) increase has been performed utilising the FLORIS wake model. The FLORIS model combines the general Jensen wake model and a model for wake deflection through yaw which has been introduced by Jiménez et al. (2010) (Gebraad et al., 2014).

Based on ECN’s results, the power scaling factor for each turbine has been derived.

First, the historical weather data of FINO3 has been analysed and for each wind speed (from cut-in speed to cut-out speed) and for each wcut-ind direction (0° to 359°) the probability of occurrence – 𝑝(𝑢) and 𝑝(𝑑), respectively – has been calculated.

Second, for each specific pair of wind speed and wind direction the joint probability of occurrence has been determined by

𝑃𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦𝑢=𝑥,𝑑=𝑦 = 𝑝(𝑢 = 𝑥 ∩ 𝑑 = 𝑦) = 𝑝(𝑢 = 𝑥) ∙ 𝑝(𝑑 = 𝑦) (3-25)

where 𝑥 is a specific wind speed between 4 m/s and 25 m/s and 𝑦 is a specific wind direction between 0° and 359°.

Third, the expected value for the power production of each turbine has been determined using the provided data set of ECN:

𝐸(𝑃𝑡𝑢𝑟𝑏𝑖𝑛𝑒) = ∑ 𝑃𝑡𝑢𝑟𝑏𝑖𝑛𝑒(𝑢, 𝑑) ∙ 𝑝(𝑢 = 𝑥 ∩ 𝑑 = 𝑦) (3-26)

where 𝑃𝑡𝑢𝑟𝑏𝑖𝑛𝑒(𝑢, 𝑑) is the calculated power output for each wind speed and wind direction

provided for each turbine in the wind farm separately by the FLORIS wake model. It takes into account that the controller is only applied to the turbine until rated wind speed (𝑈𝑟𝑎𝑡𝑒𝑑 =

11.4 𝑚/𝑠). Beyond rated wind speed the yaw-misalignment is not applied due to expected high loads and consequently, yaw-misalignment is equal to zero.

Forth, the average turbine power output for the scenario without controller and with controller has been calculated. Afterwards, a power scaling factor for each turbine has been determined by dividing the expected value by the average turbine output. In order to compare the non-controller case with the controller case, all expected values are divided by the average turbine output of the non-controller case which is set as the base value for the simulation. Thus, turbines with a power scaling factor smaller than one (𝑘𝑝𝑜𝑤𝑒𝑟 < 1) generate less power than the average turbine in the

non-controller case and turbines with a power scaling factor bigger than one (𝑘𝑝𝑜𝑤𝑒𝑟 > 1)

generate more power than the average turbine in the non-controller case.

(35)

Figure 10: Power scaling factor visualisation based on wake simulation without controller implementation

(36)

3.7.2 Updated Failure Rate Model

As a consequence of the changing load scenarios when applying yaw-misalignment (see chapter 2.3.2), operation of the wind farm will be affected as well. Therefore, it is necessary to analyse which impact that these changes on structural loads have on the turbine components’ reliability figures. In order to evaluate the impact of the controller, failure rates dependent on operation need to be determined instead of using fixed failure rates for all turbines within the wind farm. Consequently, the failure rates presented in Table 2 need to be adjusted.

In general, there are two different types of reliability models: Failure rate estimation can be performed by either applying probabilistic models or physical models. While probabilistic models are data-driven reliability models based on historical failure rate data, physical models are equation-based models which take several failure’s causes into account. (Reder, 2018)

For establishing new failure rates under application of the yaw-controller, probabilistic models cannot be used as no sufficient operational data of such a system is available. Simultaneously, physical models require a thorough understanding of all physical processes for each component leading to failures. Due to lack of knowledge how different factors influence failure rates, simplified approaches for adjusting failure rates have been developed and are explained below. Gintautas and Sørensen (2015) summarised general approaches for adjusting failure rates considering environmental and operational conditions. For the recalculation of failure rates, the following formula can be used:

𝜆𝑎𝑐𝑡𝑢𝑎𝑙 = 𝜆𝑏𝑎𝑠𝑒∙ 𝜋𝐸,𝑄,𝑅,… (3-27)

where 𝜆𝑏𝑎𝑠𝑒 and 𝜆𝑎𝑐𝑡𝑢𝑎𝑙 are base and adjusted failure rates and 𝜋𝐸,𝑄,𝑅,… are scaling factors taking

different conditions of environment and quality, but also operational conditions into account. In order to determine such scaling factors, each component of the model needs to be investigated in detail to understand possible failures, its causes and the impact of controllers and additional loads. Therefore, a general understanding of the layout of the turbine is useful to understand how a turbine works and in which points loads are introduced (see Figure 12).

(37)

In regard to the component model presented in sub-chapter 3.1.2, concepts for the following components have been developed: gearbox, generator, pitch system, yaw system, blades, main shaft, and electrical system.

The failure rate of the gearbox is based on many different influences. On the one hand, typical failure modes of bearings are axial cracks, which can lead to macropitting or splitting of the inner ring. On the other hand, the gears can fail due to scuffing, fretting corrosion or micropitting/macropitting (Sheng, 2014). In general, failures can occur either due to outer circumstances such as environmental influences or manufacturing defects or due to operational consequences. When applying the yaw controller, the outer circumstances do not change. Therefore, the failure rate is only affected by changing operation. Nejad et al. (2016) found that the load effect of the gearbox components is not correlated with the axial acceleration but are mainly affected by the torque. Also, Breeze (2016) points out that most of the wear of the gearbox is related to torque and recommends reducing it by splitting the drive train into smaller units. Consequently, the torque is found to be a good indicator how the failure rate is affected. The more torque is applied, the higher is the wear. As the torque cannot be easily simulated for the controller case over the wind farm’s lifetime, the change in power production was assumed for scaling the failure rate:

𝑃 = 𝜏 ∙ 2 ∙ 𝜋 ∙ 𝑛 (3-28) where 𝑃 is the power generated by the gearbox/turbine, 𝜏 is the torque, and 𝑛 is the rotational speed of the gearbox. Assuming 𝑛 = 𝑐𝑜𝑛𝑠𝑡𝑎𝑛𝑡, power and torque are proportional. Consequently:

𝜋𝐺𝑒𝑎𝑟𝑏𝑜𝑥= 𝑘𝑝𝑜𝑤𝑒𝑟 (3-29)

where the power scaling factor is the same as introduced in sub-chapter 3.7.1. The failure rate scaling factor for the gearbox 𝜋𝐺𝑒𝑎𝑟𝑏𝑜𝑥, which is specific for each turbine in the wind farm and

different for each case (non-controller and yaw controller case), is applied to the base failure rates for all failure modes of the gearbox introduced in Table 2. Therefore, a failure rate distribution within the wind farm for the gearbox considering the loads due to wake effects has been found. Same as for the gearbox, for generator, pitch system, yaw system, and electrical system it has been analysed which operational aspects change when applying the yaw controller. It can be assumed that the more these components are used, the higher is the wear and consequently the failure rate. Gebraad et al. (2014) stated that an optimised wind farm due to controller is not subject of an increased actuator usage in comparison to the greedy operation. As both strategies, operation without and with yaw controller follow actions when the wind direction changes, the usage of generator, pitch system, yaw system and electrical system are the same for both cases. This has been backed up by interviewing a project partner which has been involved in the development of the closed-loop yaw-controller. Therefore, the failure rate scaling factors are determined as:

𝜋𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟= 1 (3-30)

𝜋𝑃𝑖𝑡𝑐ℎ 𝑠𝑦𝑠𝑡𝑒𝑚 = 1 (3-31)

𝜋𝑌𝑎𝑤 𝑠𝑦𝑠𝑡𝑒𝑚 = 1 (3-32)

References

Related documents

Creating a flexible system, and producing the maximum energy from the wind it is one of the main aims of this thesis. The blade structure design in original form is

Having reliable supplier relationship is one of the main sources for companies’ open innovation strategy, exploring and raising the level of innovativeness. Consequently,

Index Terms: Wind Power, Power Electronics, Induction Machine, Controls (Voltage Control, Active and Reactive Power Control, Current Control, DC Voltage Control), Voltage

When estimating the electricity generation with measurement series performed on heights other than the hub height, the simulations using the forest module in WindSim yielded

It was demonstrated that by following the strategic management process, the owner can use his competencies, which are the available information he has regarding the

The buses were defined as PQ-buses, as there was active and reactive power production data and load data for all the wind turbines in the wind farm, but there was missing voltage

However, they gradually include a number of constraints: the energy leaving a turbine must be supported by a single cable; the maximum energy flow (when all the turbines produce

To address the urgent need of the wind industry for a new generation of more advanced wake models, which accurately quantify the flow properties for an entire wind farm within