• No results found

Contributions to the 3rd Budapest Conference on Soil Mechanics and

N/A
N/A
Protected

Academic year: 2022

Share "Contributions to the 3rd Budapest Conference on Soil Mechanics and "

Copied!
26
0
0

Loading.... (view fulltext now)

Full text

(1)

STATENS GEOTEKNISKA INSTITUT

SWEDISH GEOTECHNICAL INSTITUTE

No.32 SÄRTRYCK OCH PRELIMINÄRA RAPPORTER

REPRINTS AND PRELIMINARY REPORTS

Supplement to the "Proceedlngs" and "Meddelanden" of the lnstltute

Contributions to the 3rd Budapest Conference on Soil Mechanics and

Foundation Engineering, Budapest 1968

1. Swedish Tie-Back Systems for Sheet Pile Walls

Bengt Broms

2. Stability of Cohesive Soils behind Vertical Openings in Sheet Pile Walls. Analysis of a Recent Failure

Bengt Broms

a

Hans Bennermark

STOCKHOLM 1969

(2)

STATENS GEOTEKNISKA INSTITUT

SWEDISH GEOTECHNICAL INSTITUTE

No.32 SÄRTRYCK OCH PRELIMINÄRA RAPPORTER

REPRINTS AND PRELIMINARY REPORTS

Supplement to the ''Proceedings'' and ''Meddelanden'' of the lnstitute

Contributions to the 3rd Budapest Conference on Soil Mechanics and

Foundation Engineer ing, Budapest 1968

1. Swedish Tie-Back Systems for Sheet Pile Walls

Bengt Broms

2. Stability of Cohesive Soils behind Vertical Openings in Sheet Pile Walls. Analysis of a Recent Failure

Bengt Broms & Hans Bennermark

Reprinted from Proceedings of the 3rd Budapest Conference on Soil Mechanics and Foundation Engineering, Budapest 1968, Vol. 1

STOCKHOLM 1969

(3)
(4)

SWEDISH TIE-BACK SYSTEMS FOR SHEET PILE WALLS

B. B. BROMS

S\"i'ED!Sll GEOTECH:-IJCAL JNSTITUTE, STOCKHOLM, SWEDE)<

This article describes three new tie-back systems developed during the last few years in Sweden. They consist in principle of steel rods or cables which are grouted in rockor soil. The earth pressures acting on anchored sheet pile walls vary considerably. The highest values are generally obtained when the soil behind the sheet pile walls freezes and expands. The Rankine earth pressure theory is generally used to calculate the forces in the anchors, the moment distribution and required penetration depth of the sheet piles. To prevent damage of structures located close to the sheet pile wall, the pressure distribution is generally assumed to be trape­

zoidal. Failure of ancbored sheet pile walls may occur along a deep surface which extends to the far cnd of the anchor zones. The available passive Rankine earth pressure at the lower part of the sheet pile wall should be at least 50% greater than the earth pressure required to prevent failure along the assumed failure surface.

1. Introduction

Three new tie~back systems

for

sheet pile walls which

in principlc

eon­

sist of steel rods 01· cables grouted

in rock

or in soil

as illustrated in

Fig.

1 have been developed in

Sweden

by Hagconsult AB, Stabilator AB

and

Nya Asfalt AB

since the

method

was

introduced in 1959

(NORDIN

[4],

LUDVIGS­

SON

[2]).

Tie-back anchors have the advantage over

conventional bracing systems that the anchor

rods or

cables

do not interfere with

construction activities

within the

sheet

pile wall.

Experience has

furthermore

shown that blasting

can be done relatively close to

an

anchored

sheet pile wall without clamaging the anchor system

or the

sheet piles. However, the drilling of the

bore holes for

the anchor

rods or cables has

to

be done with care, otherwise electrical

cables,

water- or

sewerlines

located outside the

sheet

pile wall at the level

of the anchors may be damaged. The new anchor systems

are

generally com­

petitive with

conventional

bracing

systems

if all costs

are

considered. Due to these advantages tie-back anchors are used

extensively in Sweden.

In this article

are briefly described the

anchor

systems and the pro­

cedures followed in Sweclen for the design of anchorecl sheet pile walls.

(5)

2 B. B. BROMS v-/Gle

Soil onchor

I Anchor

zone Sheet pile woll

Rock onchor /

Rock balt/'

Fig. 1. ln-situ anchors for sheet pile walls

2. Swedish tie-back systems

2.I Hagconsult system

The

anchor system

developed hy Hagconsult AB, in cooperation with Sandvikens Jernverks AB and Atlas Copco, has been descrihed previously by

NORDIN

[5, 6]

and

by

SAHLSTRÖM- NORDIN

[7]. The distinctive feature of this

system

is that the

anchor

rods are also used as drill rods. Due to this

reason the

hardened and tempered anchor rods are

at

their lower

ends

pro­

vided with a

drill bit. The diameter of the drill bit can be varied to fit the local

conditions.

A larger diameter is generally used in

soil than in rock.

Chaiu-fed carriage mounted hammer drills

are

normally used for the installation of the anchor rods. Rock anchors are drilled approximately 3 ro into sound rock. The inclination of the anchors is generally 45°. This

system can

also be used in rock fills or moraine containing large stones or boulders.

When the desired depth has been reached cement

grout

is injected through the centre hole of the combined anchor and drill rods. After the grout has hardened the anchors are normally

test

loaded. The design loads

are

35, 45 and 65 metric tons.

The Hagconsult anchor

system can also

be used in

grave} and coarse

sand as indicated by tests carried out by

ÖHRSTRÖM and NORDIN

[8]

, NORDIN

[6] and

SAHLSTRÖM

&

NORDIN

[7]. The inclination of the

anchor

rods is in

(6)

SWEDISH TIE-BACK SYSTEMS FOR SHEET PILE WALLS 3

these materials about 20°. Cement grout is injected within the intended anchor zone for a length of approximately 5 m. The injection pressure varies generally between 5 and 20 kp/cm

2•

This method has been used in sand, moraine and heavily overconsolidated houlder clay. However, in sand

it is

recommended that the average grain size of the soil should exceed approxi­

mately 1 mm.

An advantage with the Hagconsult system is that the force in the anchor rods can be conveniently measured and adjusted after the anchors have been installed and preloaded by observing the force at which the locking nut can be released. The preload generally corresponds to 85 % of the design load to decrease the settlements of the soil hehind the sheet pile wall.

The Hagconsult System is primarily used for temporary installations.

2.2 Stabilator system

The Lindö and the Alvik drilling methods are used to drill the bore holes for the anchor rods or cables in the anchor system developed hy Stabi­

lator AB. At the Lindö method a casing which at its lower end has a cutting shoe is used during drilling through soil. The diameter of the casing varies between 70 and 205 mm. The casing and the conventional drill rods are rotated and hammered at the same time. The drill rods with 32 mm diameter have a cutting bit with carbide insert bits.

At the Alvik drilling method an eccentric drill bit which is attached to the lower end of the drill rods is used during the drilling operation. With this cutting shoe a bore hole is obtained in soil which is sufficiently large to fit a thin-walled casing with 64 to 150 mm inside diameter. Because of the eccentric system the drill rods and the drill bit can be withdrawn through the casing by turning the drill rod counterclockwise 180 degrees. The casing is advanced without rotation during drilling of the hore hole. This drilling method is often preferred when the anchor rods or cables are relatively long and when the casing is left permanently in the soil as protection against corrosion.

After the casing has penetrated approximately 20 cm into sound rock the drilling is continued with the central drill string as illustrated in Fig. 2 until a sufficient anchor length has been obtained for the rods or cables.

A length of approximately 3 m is generally sufficient in sound rock when

the design load of the anchor system is less than 45 metric tons. When the

design load is between 45 and 75 metric tons the anchor length is generally

4 m. When the design load exceeds 75 metric tons an anchor length of 5 m

is generally used. If the rock conditions are not favourable a considerably

longP-r anchor length than 5 m might be required. The inclination of rock

(7)

4 B. B. BRO)fS

anchors is about 45° while

the inclination

of soil anchors Yaries betwrt>n 10° and 45°.

Cement grout is injected at a pressure of 5 to 20 kp/cm~ into 1he bore hole through an injection pipe which reaches the bottom of the borehok.

Thereafter the anchor rods or cables are inserted into the borc hole and the casing withdrawn. Rods are mainly used whcn the design load is less than 45 metric tons. These are fastened to the wales with nuts. After the cement grout has hardened the anchors are test loaded to 90% of the yield strength of the anchor rods or cables. With the Stabilator methocl anchor forces up to 125 metric tons can be resisted permanently in rock or soil.

Fig. 2. Installation of anchor-

Advantages with the Stabilator mctho<l are

that the

area of the anchor rods or cables and thus the design load can be varicd 10 fit thc earth pressures and the dimensions of the shcet pile wall and that thc casing which is used

<luring drilling through soil prcvcnts the bore holc from collapsing.

In addition it is possible with this method to protrct the

anchor rods permanrntly against corrosion

by leaving

the casing in thc ground and by filling the casing with cement grout. It is important that the cement grout completely fills the spacc betwecn the anchor rod or cable and thc casing. Tight fitting polye1hylene l1oses are shrunk on the rods

or

cables to allow these to mo, e whcu loaded.

The rocls and cables are paintccl or grcased as a further protection against corrosion.

2.3 Nya Asfalt system

The method developed by Nya Asfalt AB is in principle similar to the

Stabilator Method. In the Nya Asfalt system the bore holes for the anchor

rods or cables are drilled by the JB-drilling method. This drilling methocl

(8)

5

~WEOISH TIE-BACK SYSTEMS FOR SHEET PILE WALLS

requires casing in the soil. The cutting shoe to the casing can in the JE-drilling mcthod be rotated independent of the casing through a slip coupling. During the drilling operation the cutting shoe

to the casing is locked to

the drill rod. Thus the cutting shoe and the central drill rods are in soil rotated and advanced as a unit. When the casing and the drill rods have penetrated about 20 cm into sound rock the cutting shoe is disengaged from the drill string. The drilling is then continued with the drill rods in a conventional manner as shown in Fig. 2. W ater or compressed air is used to remove the cuttings.

After the hore hole has been drilled the anchor rod or cable is inserted.

The anchors are then grouted in the bore hole through a tube inserted to th

0

bottom of the bore hole. After the grout has hardened the anchors are tested and preloaded.

Rods are fastencd to the wale with nuts. Cables are fastened with anchor rings and cones of type Freyssinet. With this method it is somewhat morc difficult thau with locking nuts to measure and adjust the load after installation of the anchors. An advantage with the Nya Asfalt method is that the dimensions of the rods or cables and thus the design load can be varied

to fit

the local conditions. Loads up to 100 metric tons can be resisted by each anchor in rock or in soil under favourable conditions.

3. Design pri nciples

The design principles discussed in this section are primarily intended for temporary sheet pile walls which will be used less than about two years.

If

the anchored sheet pile walls will be used for more than two years higher safety factors than those indicated in this article should be used. Furthermore,

the

stress distribution in the anchors, wales and sheet piles should also be checked for the earth pressure distribution calculated from an effective stress analysis (<J>',

c' -analysis). In addition the anchor rods or cables

must be pro­

tected against corrosion.

3.1

Failure oj in situ anchored sheet pile walls

Failures ofin situ anchored sheet pile walls have occurred. These failures

can in some cases be attributed to the axial force in the sheet pile wall caused

by the inclined anchor rods as illustrated in Fig. 3 (a).

If the penetration

depth is not sufficient the sheet piles are forced into the underlaying soil by

the axial force in the sheet piles mentioned above. When the sheet piles move

downwards they are also displaced laterally due to the inclined anchor rods

as shown in Fig. 3 (b). It also can be seen

that the axial force, the

lateral

(9)

6 B. B. BRm1s

displacement of the sheet pile wall and the settlement hehincl the sheet pile wall will increase with increasing inclination of the anchors.

The vertical force in the sheet piles is resisted hy hearing

at

the toe of the sheet piles and hy skin friction primarily along the side of the sheet piles which face the excavation. The point resistance in clay, silt and sand is small. The skin friction resistance in clays with an undrained shear strength

cu

less than 5 t

/m2

is often assumed equal to

Cu

wbile in clays with an undrained shear strength exceeding this value

Ca

= 0,5

Cu· In

sand the skin friction

·... ··.· .·· . ·-

- - - -

Verticol force in sheet pile l'IOll[from indned onchor)

·-.-:--.-:1

o) Force systern

u .

b/Foilure mechonism Fig. 3. Failure of sheet pile wall

resistance is often calculated from the assumption that the friction angle is half the angle of interna} friction of the soil. The skin friction along the opposite side depends on the relative movement of the sheet pile wall with respect to the soil hehind the sheet piles. This skin friction resistance is generally neglected in the calculations. The axial force may also cause the sheet piles to huckle if the unsupported length of the wall is large.

To decrease the risk of toe failure and of huckling the inclination of the anchor rods should be small. On the other hand, if the inclination is small the length of the anchor rods will be large.

In a few cases anchor rods have ruptured after they have heen tested.

However, these local failures have not resulted in general failures since the overall anchor system, the wales and the sheet piles have heen design.ed to resist the load increase caused hy the rupture of any anchor rod or cahle.

Failures hy exceeding the moment resistance in the sheet piles or the horizon­

tal

wales have not occurred in Sweden to the author's knowledge.

(10)

SWEDISH TIE-BACK SYSTE11S FOR SHEET PILE WALLS 7

3.2.

Earth pressure calculations

The earth pressui-es acting on in-situ anchored sheet pile walls vary.

The highest earth pressures and the highest anchor forces often develop during the fall when the water content of the soil behind the sheet pile wall increases during the rainy season or the soil freezes and expands. The increase can be !arge if the

soil

is frost sensitive and the length of the anchor rods or cables is relatively small. Under unfavourable conditions the earth pressure may approach or even exceed the totaloverburden pressure. During the thawing period in the spring the earth pressure and the anchor forces may also increase.

a b

1,6 PA - h -

f -

-1

I

-\-

'

I 0,'2h

1 I Active Ronkine 0,6h

----earth pressure

I

'

0,'2h

'

Cohes1anless srnl (low relative density) and col1esi1e soi:s

Fig. 4. Earth pressure distribution

(a) Earth pressure distribution in cohesive soils according to Rankine (b) Trapezoidal earth pressure distribution in cohesive and cohesionless soils

The lowest earth pi-essures are generally obtained in the late summer

just

before the rainy season. Due to lack of test data it is not possible at present to predict the seasonal variations of the earth pressures and of the anchor forces. Additional test data are therefore highly desirable.

The active earth pressure acting on in-situ anchored sheet pile walls is generally calculated by the Rankine earth pressure theory. The tension which theoretically develops at the ground surface to a depth of 2 cu/Y is, however, neglected in the calculations. This

t ension

is replaced by a hydro­

static

water pressure as shown in Fig. 4 (a). It is thus assumed that the surface cracks in the tension zone will be filled with water during the life of the structure.

If buildings, sewer or water lines which might be damaged by excessive

settlement s are located close to t

he sheet

pile wall and if several rows of

anchors are used the earth pressure distribution is assumed to be trapezoidal

as shown in Fig. 4 (b). The earth pressure is thus assumed to increase linearly

(11)

8 B.B. BROMS

from the ground surface to a depth of 0,2

h,

where

h

is

the total depth of the

excavation. Below this depth

the earth pressure is 1,6

Pa/h, ,vhere Pa is the total active earth pressurc ahove the hottom of the excavation.

In very soft

clays with an undrained shear strength less than 1,0 t/ m

2 thc

lateral earth pressure is often assumed to be equal to the total oyerhurden pressurc. Th<' earth pressme in this case is cquivalcnt with the pressure from a fluid with the same unit weight as the soil.

3.3.

Length oj anchor zo11e

The rcquircd length of the anchor zone in rock is generally 3, 4 and 5 m for granite and gneiss or for equivalent rock materials with only few and widely spaced surface cracks whcn the design load is less than 45 m

etric tons, betwecn

45 and 75 metric tons or larger than 75 metric tons, r espectively. A con­

siderahly longer anchor zonc might be required when the crack spacing is small or the cracks are unfavourahly oriented. The orientation of the crack is considered unfavourahle if a wedge of rock can be pulled loosc

hy thc

anchors. It is furthermore required that the distancc hctwecn thc anchor zoncs for adj acent levels of anchors in rock should he

at least 2,5

m according

to Swedish

practice.

There is no method availahle at present

to calculate in

advance the length of the anchor zone which is required in coarse sand and gravel. The ultimate strength of the in-situ anchors in thesc materials will depend on such factors as the effective grain size, the grain size distribution of the surrounding soil, the composition of the grout, the injection pressure as well as the geometric configuration of the anchor zone. The rcquired length of the anchor zone is in these materials generally determined hy field loading tests.

LuNDAHL-ADDING

[3] have discussed design methods for anchors installed in silt. Failure is assumed to be caused hy pull-out. The failure load is in this case dependent of the skin friction resistancc along the grouted part of the anchor rod as shown in Fig. 5

. In

cohesionless soils (sand and silt) the skin friction rcsistance

't'a

is dependent of the avcrage effective over­

hurden pressure

ö'v at

the level of the anchor zone according to the equation

't'a

= K

0

ä.,

tan

<I>

a (1)

where K

0

is an earth pressure coefficient.

It is rccommended to use

K

0

= 1 when the r elative density of the surrounding soil is high aud K

0

= 0,5 wheu the relative density is low. However, it is likely that this coefficient is depen­

dent on the injection pressure. The friction angle

<Pa

is dependent on the

roughness of the contact surface hetween the anchor and the surrounding

soil. Test results indicatc that this friction angle is approximately equal to

the angle of interna! friction

. It is recommended to use <Pa

= 30° for medium

(12)

;rn EDISH TIE-BACK SYSTEMS FOR SHEET PILE WALLS g

to fine sand and <Pa = 25 for silt in the calculations

if results from field or

laboratory experiments do not indicate otherwise. The effective overburden pressure a

0 at

the level of the anchor zone is dependent on the location of the ground water table and the unit weight of the overlying soil. The effectiYe overburden pressure may change during the life of the sheet pile wall due to excavation or a change of the ground water table. This factor must be considered in the design.

_- . I

I I

/ I

I I \

I \ .l

I I

I'-45°+rf,/2

'

Minimum required pooetrot1on depth

Fig. 5. Calculation of required anchor length in medium to fine sand, silt and stiff clay

A similar calculation method may be used for anchors in heavily over­

consolidated clay with an undrnined shear strength exceeding 5 t/m

2 •

Such anchors are often designed for a skin friction resistance

•a

equal to 0,5

Cu,

where

c11

is the undrained shear strength of the soil determined by unconfined compression tests.

3.4. Failure along deep lying failure surface

The location of the anchor zone is governed by failure by sliding along

the rnpture surface shown in Fig.

6 as discussed

by SAHLSTRÖM-NORDIN

[7]

and by LuNDAHL-ADDING [3]. The rupture surface is assumed to extend from a point B located 2 m from the lower end of the anchor zone to a point C on the sheet pile · wall. Point C corresponds to the minimnm penetration depth required to prevent failure. Point B has been chosen to take into account differences between actual and assumed length of the anchor zone and varia­

tions of the location of the critical failure surface. The forces initi~ting failure

are the force P

1

which acts along A- B and the weight W of the sliding mass

of the soil. The forces preventing failure are the reaction force Q, the anchor

force

T,

the toe resistance

V

and

the passive

earth pressure

Pp at the lower part of the sheet pile wall above point C. The anchor force T

acts al ong B- F,

(13)

10 B. ll. BRmIS

the

section

of the anchor zone

located

hetween the assumed failure

surface

and the end of the anchor zone. This force

is

generally neglected

in

the calculations. The reaction force V at the toe of the sheet pile wall which is equal to the

vertical force in the sheet

piles is dependent of the inclination of the anchor rods or cahles. The force

(Pa)required

which is necessary to prevent failure along the assumed failure surface can he

calculated

from the force

E

D 01Assumed foilure

surfoce

,, - C

(Pp)required

l IV

T V

\_Pp)ovoiloble ) 1,5

(Pp) required

w

bJc-arce polygon

Fig. 6. Failure along deep failure surface

polygon

shown

in

Fig.

6 (h). This force

should

be less than

(Pp)availab1e/

F, where

(Pp)available

is the passive Rankine

earth

pressure force above point C and Fis a

safety factor.

This safety factor is

generally assumed equal to 1,5.

In some cases it is desirable to repeat the calculations for a numher of failure

surface

which intersects the anchor zone

at

different

distances

from its lower end. The failure surface which gives the lowest safety factor with respect to the availahle total passive Rankine earth pressure corresponds to the critical failure

surface

of the system.

In addition the stahility along

the

assumed failure surface should

he

checked

for the case when the friction angle for the force Q is

equal

to

<Pred•

This

friction angle is calculated from tg

<l>red

= tan <P/

1,3.

The passive earth

pressure

(Pp)required which

is required to prevent failure

along

the assumed

(14)

11

SWEDISH TIE-BACK SYSTEMS FOR SHEET PILE WALLS

failure surface should be less than the available earth pressure force

(Pp)avnilable

above point C.

It should, however, be pointed out that the assumed plain failure sur­

face B -C corresponds to a higher safety factor than a convex failure surface through the same points. The difference between the two failure surfaces is generally small and is neglected in the calculations.

An additional requirement for tie-back anchors in soil is

that

no part of the anchor zone should be located within the active earth zone which affects the earth pressure on the sheet pile wall. This zone is determined by drawing from point C on the sheet pile wall a straight line which is inclined

(45 +

<l>/2)

with the horizontal. The anchor zone should furthermore be

l

ocated at least five meters below ground surface.

The anchor rods or cables may be damaged by settlements of the soil behind the sheet pile. If this is the case the anchor rods or cables should be protected by a casing. The diameter of the casing should be sufficiently large to allow for the settlements at the level of the anchors.

3.5.

Load tests oj in-situ anchors

Each anchor should be tested to a load not

exceeding

75% of the ultimate strcngth or 90 % of the yield strength for materials with a flat stress­

strain relationship at

yielding.

An additional requirement is

that the test

load should not exceed 75 % of the ultimate strength of splices or connections.

The test load should b

e kept constant for at least 10 minutes.

If the spacing of the anchors is less than 2,5 m at any level, three anchors should be tested at the same time. All anchors should be loaded consecutively.

The test load on the

same

three anchors should be maintained for at least five minutes. Thus each anchor will be loaded for at least 15 minutes.

In coarse sand and gravel several anchors

may be interconnecte d by the injection of the cement grout.

In this

case all anchors at the same level should b

e

tested at the same time

.

1f it can be shown by calculations that the safety factor against pull-out of the anchors is greater than 1,5 with respect to the design load, only three of the anchors should be tested at the same time.

The anchors may creep at the test load. Then the applied load should be d

ecreased until anchor ceases

to move. This load is defined as the ultimate strength of the anchor. The test load used in the calculation of the allowable load is 80

%

of the ultimate strength defined above.

3.6.

Allowable load on anchors and wales

The allowable load in the anchor rods or cables is the test load divided

with a factor equal to 1,3

.

The load on the anchors is calculated at working

loads from

the

assumption that the horizontal wale is supported hy a

series

(15)

12 B. B. BROMS

of unyielding rigid supports.

It is furthermore assumed that

the load from the sheet piles is uniformly distributed along the horizontal wale beam.

An additional requirement is that the force in the anchors should not exceed the test load if any of the anchor rods or cables ruptures. Also the maximum stress in the wales should not in this case exceed the yield strength of the material in the wales or the sheet piles. The moment distribution in the wales is calculated from the assumption

that the load from the

sheet piles is unifo,·mly distributed and that the wales are supportecl on

a series

of elastic springs. The spring constant of the support is dependent on the length and the dimensions of the anchor rods or cables. This case generally governs the dimensions and the spacing of the anchors and of the wales

3.7.

Preloading of anchor rods and cables

To decrease the settlement behind an anchored shect pilc wall the anchors are preloaded. The preload often corresponds

to

70-80% of the earth pressure distribution shown in Fig.

4

(b). The preload is thus depenclent of the soil condition, and of the depth of the excavations.

If

the spacing between two anchors is small as is often the case at the free end of a ,vale the preload in the anchors should be half the preload on the reminder of the anchors. The load in thc anchors should be checked and adjusted cluring the excavation if structures which can be damaged hy settle­

ments are located close to the sheet pile wall.

3.8.

Toe anchors

Rock holts or dowels are often usecl to anchor the toe of sheet piles driven to rock. The purpose of these anchors is to prevent the toe of the sheet pile wall from sliding along the rock surface. Rock bolts which are used as toe ancbors should be designed for

a moment which corresponcls to a

moment arm of 10 cm. The total length of the bolts should be at least 1,0 m. Of this length at least 0,5

rn

should be in rock. The diameter of the rock bolts varies generally between 45 and 100 mm. Furthermore at least every second sheet pile should be anchored. Anchor bolts are not allowed in Sweden in morain or fractured rock. The maximum horizontal force which is allowed in

a

rock bolt is 12 metric tons. Rock bolts can only be used as anchors when the total horizontal force is less than 15 metric tous/m. Rock bolts are geuerally iustalled through

a casing

welded to the sheet piles or by drilling through the over­

burden.

It

is important to determine the distance between the tip of the sheet

piles and the rock surface.

If

this distance is excessive (larger than 10 em)

then additional rock bolts might be required. The distance to rock cau be

(16)

SWEDISH TIE-BACK SYSTE)l!:i FOR SHEET PILE WALLS 13

detennined

during the drilling of the holes for the rock bolts by filling the lower parts of the

casing for the rock

bolts with concrete before chiving. The

concrete plug also protects the casing

during drivin· g

of the sheet pilcs.

Additional toe ancho1·s

can

also be installed after the

sheet

pile

wall

has been

exposed

if it is found <luring the

excavation that some

of the

sheet

piles

have

not reached rock. Toe anchors will also be required if blasting is donc close to the sheet pile wall. In this case inclined steel rods with a length of at least 2 m

are used which are grouted in rock. The length and the diameter of the nnchor rods

are chosen to fit the quality of the underlaying rock.

*

The design principles in this article except for the earth pressure calculations have been discussed by a committee with the following members: A. HELLGREN (Chairman), P.-O.

NORDIN (Secretary), H. LINDQVIST, G.-M. BENGTSTELIUS, S. BERGSTRÖM, B. LuNDAHL and S. WIDING.

REFERENCES

1. BERGST!lÖM. U.- STROKIRK, E.: Spontförankring med dragstag. Byggmästaren, 41 (1962), 159-160

2. Lt:DVIGSS0N, B.: Dragförsök med bergförankringar av förspänningsstål. Byggnadsingenjören, 40 ·(1961) 50- 51, 62.

3. LUNDAHL, B.- ADDING, L.: Dragförankringar i flytbenägen mo under grundvattenytan.

Byggmästaren, 44 (1966), 145- 152

4. ;.\°0RDIN, P. 0.: Spontförankring med dragstag. En ny lösning av ett svårt problem. Bygg- mästaren, 41 (1962), 43- 48

5. ~0RDIN, P .-O.: In-Situ Anchoring. Rock Mechanics and Eng. Geology, 4 (1966), 25 - 37 6. )l°ORDIN, P.-O.: In-Situ förankring. Byggmästaren, 43 (1964), 261-268

7. SAHLSTRÖM, P.-O.- NORDIN, P .-O.: In-situ förankring i jord. Väg- och vattenbyggaren, (1966), 271- 279

8. ÖHRSTRÖM, G.-NORDIN, P.-O.: Dragförankring i friktionsjordarter. Byggmästaren, 41 (1962), 221- 226

CHCTeMbl aHl(epOBl(H WBCACl(HX wnyHTOBbIX CTeH

15. 15. 15pOAfC

ABT0P om1Cb1BaeTTpll ,\leT0Aa aH1<ep0BKH, pa3pa60TaHHblX3a noCJJe.D.Hlle rQ.LJ.bl B Wsel(HH.

no Cyll\eCTBY aHI<ep0BI<II C0CT051T H3 CTanbHblX CTep)I<HeH HnM I(a6ene11, I<OTOpble I<pen51TC51 3a cTeHot'1 nyTeM 3aI<penneHH51 rpyHTa.

)].asneHHC rpy1-1Ta, .D.eHCTBYIOll\Ce Ha aHl<epOBI<0H 0TT51HYTblC wnyHT0Bble CTeHbl, M3Me­

H51eTC51 s 3Ha'l1ne,1hHot'1 Mepe. Ha116onhwero 3Ha'leHH51 .LJ.0CT1-iraeT np11 3aMep3aHHM 11 pacw11- pem111 HaCblITM. Bo00ll\e .D.n5l paC'ICTa aHI(epH0H CHnhl, pacnpe.D.eneHM51 M0MeHT0B 11 TpeoyIO­

ll\eHC51 rny611HhI 3a611B1<H np11MeH5IeTC5I Te0pH5I Rankine no .D.asnem110 rpyHTa. B uen51x npe­

JI.0TBpaIUeHM51 yll\epoa, onacHoro .n.n51 coopy)l(eH11il:, pacnono>1<eHHhIX s6n11311 wnyttT0BhIX CTeH, pacnpe.D.eneHHC Ha11p51)1(eHHt'1 npHHHMaCTC51 B qiopMe Tpane3bl (CM. pHC. 46).

Y wnyHT0BblX CTeH CK0nb)l(CHHC M0)KCT B03HlfäHYTb BA0nh rny601<one)I<aw;11x TI0Bepx­

HOCTCH. ,Uei1cTBy10IUee .n.asnett11e rpyHTa no Rankine A0JI)l(H0 6h1Tb Ha 50% 6onbllle, 'leM Benil'IIIHa, HC06X0JI.MMa51 ,!1,n51 npe.D.0TBpall\eHH51 o6pyweHH51.

Bengt B. BROMS, Director of the Swedish Geotechnical Institute, Banergatan 16.•

S tockholm. Sweden

(17)
(18)

STABILITY OF COHESIVE SOILS

BEHIND VERTICAL OPENINGS IN SHEET PILE WALLS

AXALYSIS OF A RECENT FAILURE

B. B. BROMS- Il. BENNERMARK

S\'l"EDISH CEOTECIJXICAL I:"iSTITUTE, STOCKROL~!, SWEDEN

The stability of a clay mass located behind a vertical opening in a sheet pile wall has been analysed earlier by the authors. Theoretical calculations and field observations showed that failure may occur when the ratio of the total overburden pressure and the undrained shear strength of the soil at the opening is 6 to 8. A failure which recently took place where approximately 30 m3 of clay flowed thi:ough a vertical opening at the bottom of a sheet pile wall has been analysed by the proposed method. The area of the opening was 0,2 m~. The failure occurred when tbe ratio yh/cu was 7,5. This failure indicates that even very small openings in a sheet pile wall can cause extensive damage under unfavourable conditions and that sucb openings must be considered in deep excavations in soft soils.

1. Introduction

The

stability of a

clay mass located hehind a

vertical opening

has heen

analysed

previously [2]. In

the proposed method it was

assumed that failure

occurred

along a cylindrical

failure surface

as illustrated in

Fig. la. The

failure

surface extends from the underside of the opening to a

point located approximately

at the diameter or the height of the opening ahove

the hole.

It is furthermore assumed that the

opening

is located

at

a depth

exceeding

four times the height of the opening helow the ground surface. The suggested method is

similar to that proposed in [l] to predict hottom heave of excava­

tions in clay.

The analysis indicates that failure will occur when the ratio of the total overhurden

pressure yh

at the level of the opening and the average undrained shear strength

cu of the

soil along the

failure

surface

is larger

than 6

to

8 (Fig.

lh). Also results from lahoratory and field

experiments

appear

to sup­

port the proposed method of analysis.

Availahle test data indicate that failure can take place when the ratio

,yh/cu is as low

as 6.

2. A recent failure

A failure which

recently took

place close to Upplands

Väshy

ahout

20

km northwest of Stockholm, provided another opportunity to check the

proposed method. The failure occurred

at

the hottom of

an approximately

(19)

_ _

2 B. B. BRmIS-H. BEN:\'ER~IARK

/

,,

, f

Opening - ~ Failure surfoce

o

,/I \\

I

' ' '

- - - ' - - " " - "

' "

·'

Fig. 1. Stability of clay at a vertical openiug.

Assumed failure surface (left). Failure conditions (right)

Legend x Vane boring O w'eight sounding

test

@

Soil sampling

Exco­

votion I I Cracks , I

I 1 I I I I I I

A I I

t @

X ,JA

0

Crater -( , Sheet pile

1 \ woll

I \

I \

I \

I \

\ I

\ I

\ I

0

Scaie

5 10m

\

\ '-

I I

'-...

_

.,,,,. / /

Fig. 2. Plan of excavation

(20)

3 STABILITY OF COHESIVE SOILS

8 m deep

excaYation

m clay where sheet piles had been driven in the fall

of 1965. The excavation

is located not far from the place where a similar slide had occurred [2]. The dimension of the excavation is

shown

in Figs 2

and 3. The sheet

piles were driven through approximately 8 m of clay down

to rock. During excavation it was found that one the sheet piles did not

reach the rock. The

soil

behind the

sheet

pile wall was

exposed

for a height

/ Sheet pile wall

0 '2 3 4 5m

I

Fig. 3. Section A- A through sheet pile wall

of about 0,8 m between the bottom of the sheet pile and the underlaying rock.

The

exposed area was approximately 0,2 m2

During the month of May 1966 approximately 30 m

3 of clay

flowed

suddenly through the

opening in the

sheet

pile wall into the

excavation.

At the same time a

crater approximately 2 m deep and

5 m in diameter, formed outside the sheet pile wall ("Crater" in Fig. 3).

Cracks which extended

partly around the excavation were also observed. The location of these cracks

is

shown in Fig. 2.

3. Soil conditions

The stability

of

a vertical

hole is, according to the analysis presented

previously, dependent of the magnitude of the total overburden pressure

at the leve! of the opening and the

undrained

shear strength of the soil.

(21)

4 B. B BROMS- H. BE)l!NER)IARK

The thickness of the different

soil strata and the depth to firm bottom

were determined by the Swedish weight

sounding

method

(Statens

Järn­

vägar

[5]).

The soil at the test

site consists

of grey or brown-grey

clay with sand

seams to a depth

of approximately 3

m below the ground

surface

as

shown jn Fig. 4.

Below this layer is a brown-grey varved clay to a depth of approxi-

I

Undroined

I

oept Soil type !sheor sheng'lj ;

I

w i WF Sensitivity

m ,

t

/m~ lt/m 3 % '¼ rotio

6

'20 40 60 Groy to

brown

clay w/

]

1,65

sand 'f !

2 seams

i

1.86 21

t

1

: Fall-cane 1.60 59 44 l'f ,,,ytest

4 Brown 1.64 66 50 \ I \)'

~ ; I

gray j

vorved 1,66 62 47 1 I ~

6 clay

*

I

r

\

47 38 it I ·

' ... ,

1,88 , 32 27 I

" ' ._

i ~

8 Fine sond / 2,02 I 25 Vtes anf

I

Undrained sheor strengtb.:..

Vane test x-x Woter content : w Unconfined com·o----<> Finess runber : w, pression test Unit weight : 0 Foll-cone test -

Sensitivity

Field vanetest x---x Foll-cone test .._..

Fig. 4. Soil properties

mately 8,0 m. The

varved clay

is underlain b

y a

thin layer

of fine sand and

by rock.

The undrained

shear strength

of the clay

was

measurecl by fi

elcl vane tests and by unconfined compression tests on samples taken with the Swedish standard

piston

sampler (Swedish Committee on

Piston

Sampling

[6]).

The shear strength was also determined by the Swedish fall-cone test

[3]. In addi­

tion the

water content,

unit

weight and fineness

number

were

m

easured.

(The finenes

s

number

WF

is equal

to

the water content when a cone w

eighing 60 g

pen

etrates 10 mm

under its

own weight

inta

a

r

emoulded sample· of

clay. The apex

angle of the cone is

60°.

KARLSSON

[4] has shown that the fineness numb

er is

approximately equal to the liquid limit.)

The

water ·content of the varved

clay

clecreased with depth.

It was

approximately 50% higher than the fineness number or the liquid limit of

the

soil.

The undrained shear

strength

measured by fall-cone, Yane and

(22)

STABILITY OF COl!ESIVE SOILS 5

unconfined compression tests increased from 1 t/m

2 at a depth of approximately

3 m below the ground surface to about 2 t/m

2

at the bottom of the clay layer.

The sensitivity was determined by vane and fall-cone tests. The field vane test indicated a sensitivity ratio hetween 5 and 15. The sensitivity ratio determined hy the fall-cone varied hetween 24 and 67. It is prohable that the high sensitivity of the clay can explain why the extent of the failure was relatively large considering the small size of the opening and why the failure occurred suddenly.

4. Analysis of failure

The lower part of the sheet pile where the failure occurred was located approximately 6, 7 m below the original ground surface. This depth corre­

sponds to a total vertical overhurden pressure before the failure of approxi­

mately 11,2 t/m

2 •

It can be scen from Fig. 4

that the average undrained

shear strength of the varved clay between 5,5 m and 8,0 m below the ground surface is 1,5 t/m

2

This undrained shear strength of the clay corresponds to a ratio of vertical total overburden pressure and undrained shear strength equal to 7,5. This value is in agreement with the results reported previously.

It

should, however, be noted that failure occurred approximately half

a year after the excavation was completed and that the failure occurred rapidly once it was initiated. The delay is probably caused by the

small

size of the opening (0,2 m

2) .

Also erosion of the fine sand at the bottom of the

excavation has prohably

contributed to the initiation of the failure.

Few failures which have heen caused by flow thrnugh a vertical opening have b

een

reported in the literature. Additional test data are highly desirable so that the validity of the proposed method of

analysis can be checked.

*

This investigation has been partly snpported financially by the National Swedish Council for Building Research. ·

REFERENCES

I. BJERRUM, L.-EIDE, 0.: Stability of Strutted Excavations in Clay. Geotechnique, 6 (1956, 32-47

2. BROMS, B. - BENNERMARK, H.: Stability of Clay at Vertical Openings. Proc. ASCE J.

Soil Mech. a. Found. Div., 93 (1967), 71-94

3. HANSB0, S.: A New Approach to the Determination of the Shear Strength of Clay by the Fall-Cone Test. Proc. Royal Swed. Geotechnical lnstitute, No. 14 (1957), 46

4. KARLSSON, R.: Suggested Improvements in the Liquid Limit Test with Reference to Flow Properties of Remoulded Clays. Proc. 5th int. Conf on Soil Mech. a. FoundEngng.,l (1961), 171-184

5. Statens Järnvägar: Geotekniska Kommissionen, 1914-1922, Slutbetänkande (Swedish State Railways, 1922. The Geotechnical Commission, 1914- 1922, Final Report).

Geotekn. Medd., Nr 2 (1922), Stockholm.

6. Swedish Committee on Piston Sampling, Standard Piston Sampling. Proc. Swed. Geotechn.

lnst. , 19 (1961), 45

(23)

6 B. B. BROMS-H. BE "NE)!ARK

YCTOii'IHBOCTb CB.R3HblX rpyHTOB aa sepTHl{aJibHblMH npoeMaMH wnyHTOBblX CTCH.

HCCJICAOBaHHC o6paaosamrn npoHCWCAlllero HCAaBHO 06BaJia

E. E. Epo,11c- X. Ee1mep,11ap,c

ÅBTOpbl y)l(e pattee 3amIMaJil1Cb 11CCJieAOBaHIIeM YCTOli'11180CTII .\\acc1rna r:11-IHbI, pacno­

JIO)l(eHHOrO 3a BepTHKaJibHbIM npoeMOM, o6pa30BaBlllHMC.R B lllflYHTOBO/:'I CTeHe. Teopen1,1ec1<11e pac'!eTbl [,[ HaOJIIOAeHH.R ITOI(a3aJ111, 'ITO o6pyllleHHe HaCTynaeT B TOM CJiy'!ae, I<Or.Qa OTHOllleHHe BepT11KaJI&Horo peocTaT11'1ecr<oro ttanpm1<eH11.R 11 conpoT11BJieHIIe cpeay rpyttra, onpeAeJieHHoe B COCTO.RHlll1 cocraBJl5Ier 6- 8.

Ilpu no:.1ol.l.(11 npeAJIO)KeHHoro MeToti:a 11ccne1i:osatto npo11cllleti:lllee HeAaBHO 06pyllleH1re rpyHra, npH l(OTOpOM rJIHHbI 061,eMOM np116JI. 30 ,112 BbITeKJIH y HH)l(HeH tJaCTH illITYHTOBOli CTeHbI tJepea npoeM paaMepoM a 0,2 ,112• 06pyllleH11e npo1130ll1JIO np11 y h/cu

=

7,5. 06paaoaaH11e o6pyll1eHH.R yI<a3bJBaeT Ha TO, 'ITO npoeMbI Aa)l(e He60Jibll10ro pa3Mepa MoryT np11tJHHHTb 3Ha­

'IHTeJI&Hbiti y°l.l.(ep6; BCJie.QCTBHe CKa3aHHbIX, np11 OTKpblTMH rny60KHX J<OTJIOBaHOB B .\UlrKIIX rpyHTaX HeJJb3.R He npHH.51Tb BO BHHMaHMe ra1<11e npoeMhl.

Bengt B. BROMS, Director of the Swedish Geotechnical lnstitute Banergatan 16., Stockholm. Sweden.

Hans BENNERMAnK, Civil Engineer. Swedish Geotechnical lnstitute Banergatan 16., Stockholm. Sweden.

(24)

STATENS GEOTEKNISKA INSTITUT

Swedish Geotechnical lnstitute

SÄRTRYCK OCH PRELIMINÄRA RAPPORTER Reprints and preliminary reports

Pris kr.

(Sw. ers.) No.

Out of 1. Views on the Stability of Clay Slopes. J. Osferman 1960 print 2. Aspects on Some Problems of Geotechnical Chemistry. 1960 »

R. Söderblom

3. Contributions to the Fifth lnternational Conference on Soil Me­ 1961 » chanics and Foundation Engineering, Paris 1961. Part I.

1. Research on the Texture of Granular Mosses.

T. Ka/lsfenius & W. Bergau

2. Relationship between Apporent Angle of Friction - with Ef­

fective Stresses as Parameters - in Drained and in Conso­

lidated-Undrained Trioxial Tests on Saturated Cloy. Nor­

mally-Consolidated Cloy. S. Odenstad

3. Development of two Modern Contlnuous Sounding Methods.

T. Kallstenius

4. In Situ Determination of Horizontol Ground Movements.

T. Kal/stenius & W. Bergau

4. Contributions to the Fifth lnternational Conference on Soil Me- 1961 5:- chanics and Foundation Engineerlng, Paris 1961. Part Il.

Suggested lmprovements in the Liquid Limit Test, with Refe­

rence to Flow Properties of Remoulded Clays. R. Karlsson

5. On Cohesive Soils and Their Flow Properties. R. Karlsson 1963 10:-

6. Erosion Problems from Different Aspects. 1964 10:-

1. Unorthodox Thoughts about Filter Criteria. W. Kje/fman 2. Filters as Protection against Erosion. P. A. Hedar

3. Stability of Armour Layer of Uniform Stones in Running Water. S. Andersson

4. Some Laboratory Experiments on the Dispersion and Ero­

sion of Clay Materials. R, Söderbfom

7. Setflement Studies of Clay. 1964 10:-

1. lnfluence of Lateral Movement in Clay Upon Settlements in Some Test Areas. J. Oslerman & G. Lindskog

2. Consolidation Tests on Clay Subjected to Freezing and Thaw­

ing. J. G. Stuart

8. Studies on the Properties and Formation of Quick Clays. 1965 5:- J. Osterman

9. Beräkning av pålar vid olika belastningsförhållanden. B. Broms 1965 30:- 1. Beräkningsmetoder för sidobelastade pålar.

2. Brottlast för snett belastade pålar.

3. Beräkning av vertikala pålars bärförmåga.

10. Triaxial Tests on Thin-Walled Tubular Samples. 1965 5:- 1. Effects of Rotation of the Principal Stress Axes and of the ln­

termediate Principal Stress on the Shear Strength.

B. Broms & A. 0. Casbarian

2. Analysis of the Triaxial Test-Cohesionless Soils.

B. Broms & A. K. Jamat

11. Något om svensk geoteknisk forskning. 8. Broms 1966 5:- 12. Bärförmåga hos pålar slagna mot släntberg. B. Broms 1966 15:- 13. Förankring av ledningar i jord. 8. Broms & 0. Orrje 1966 5:- 14. Ultrasonic Dispersion of Clay Suspensions. R. Pusch 1966 5:- 15. lnvestigation of Clay Microstructure by Using Ultra-Thin Sections. 1966 10:-

R. Pusch

16. Stability of Clay at Verfical Openings. B. Broms & H. Bennermark 1967 10:-

(25)

Pris kr.

No. (Sw. crs.J

17. Om pålslagning och pålbärighet. 1967 5:-

1. Dragsprickor i armerade betongpålar. S. Sahlin 2. Sprickbildning och utmattning vid slagning av armerade

modellpålar av betong. B-G. Hellers

3. Bärighet hos släntberg vid statisk belastning av bergspets.

Resultat av modellförsök. S-E. Rehnman 4. Negativ mantelfriktion. B. H. Fel/enius

5. Grundläggning på korta pålar. Redogörelse för en försöks­

serie på NABO-pålar. G. Fjelkner 6. Krokiga pålars bärförmåga. B. Broms

18. Pålgruppers bärförmåga. B. Broms 1967 10:-

19. Om stoppslagning av stödpålar. L. Hel/man 1967 5:- 20. Contributions lo the First Congress of the lnternational Society of 1967 5 :-

Rock Mechanics, Lisbon 1966.

1. A Note on Strength Properties of Rock. B. Broms 2. Tensile Strength of Rock Materials. B. Broms

21. Recent Quick-Clay Studies. 1967 10:-

1. Recent Quick-Clay Studies, an lntroduction. R. Pusch 2. Chemical Aspects of Quick-Clay Formation. R. Söderblom 3. Quick-Clay Microstructure. R. Pusch

22. Jordtryck vid friktionsmaterial. 1967 30:-

1. Resultat från mätning av jordtryck mot brolandfäste.

B. Broms & I. Inge/son

2. Jordtryck mot oeftergivliga konstruktioner. B. Broms 3. Metod för beräkning av sambandet mellan jordtryck och de­

formation hos främst stödmurar och förankringsplattor i friktionsmaterial. B. Broms

4. Beräkning av stolpfundament. B. Broms

23. Contributions lo the Geotechnical Conference on Shear Strength 1968 10:- Properties of Natural Soils and Rocks, Oslo 1967.

1. Effective Angle of Friction for a Normally Consolidated Clay.

R. Brink

2. Shear Strength Parameters and Microstructure Character­

istics of a Quick Clay of Extremely High Water Content.

R. Karlsson & R. Pusch

3. Ratio c/p' in Relation to Liquid Limit and Plasticity Index, with Special Reference lo Swedish Clays.

R. Karlsson & L. Viberg

24. A Technique for lnvestigation of Clay Microstructure. R. Pusch 1968 22:- 25. A New Settlement Gauge, Pile Driving Effects and Pile 1968 10:-

Resistance Measurements.

1. New Method of Measuring in-situ Settlements U. Bergdahl & B. Broms

2. Effects of Pile Driving on Soil Properties. 0. 0rrje & B. Broms 3. End Bearing and Skin Friction Resistance of Piles.

B. Broms & L. Hel/man

26. Sättningar vid vägbyggnad 1968 20:-

Föredrag vid Nordiska Vägtekniska Förbundets konferens i Voksenåsen, Oslo 25-26 mars 1968

1. Geotekniska undersökningar vid bedömning av sättningar.

B. Broms

2. Teknisk-ekonomisk översikt över anläggningsmetoder för reducering av sättningar i vägar.

A. Ekström

3. Sättning av verkstadsbyggnad i Stenungsund uppförd på normalkonsoliderad lera.

B. Broms & 0. 0rrje

27. Bärförmåga hos släntberg vid statisk belastning av 1968 15:- bergspets. Resultat från modellförsök.

S-E. Rehnman

(26)

I

,I

.

I

I

No.

Prl1 kr.

(Sw. en.) 28. Bidrag till Nordiska Geoteknikermötet I Göteborg den

S-7 september 1968.

1968 15:-

1. Nordiskt geotekniskt samarbete och nordiska geotekniker­

möten. N. Flodin

2. Några resultat av belastningsförsök på lerferrang speciellt med avseende på sekundär konsolidering.

G. Llndskog

3. Sättningar vid grundlöggning med plattor på moränlera i Lund. S. Hansbo, H. Bennermark & U. Klhlblom

4. Stabilffetsförbättrande spontkonstruktion för bankfyllningar.

0. Wager

S. Grundvattenproblem i Stockholms city.

G. Llndskog & U. Bergdahl

6. Aktuell svensk geoteknisk forskning. 8. Broms 29. Classificatlon of Soils wifh Reference to Compadlon.

B. Broms & L. Forssblad

1968 5:-

30. Flygblldstolkning som hjälpmedel vid översiktliga grund undersökningar.

1969 10:-

1. Flygblldstolknlng för jordartsbesfämnlng vld samhällsplanering 1-2.

U. Kihlblom, L. Viberg & A. Heiner

2. Identifiering av berg och bedömning av jorddjup med hjälp av flygbilder.

U. Kihlblom

31. Nordiskt sonderingsmöte i Stockholm den S-6 oktober 1967.

Föredrag och diskussioner.

1969 30:-

32. Contributions to the 3rd Budapest Conference on Soll Mechanlcs and Foundatlon Engineering, Budapest 1968.

1969 10:-

1. Swedish Tie-Back Systems for Sheet Pile Walls.

B. Broms

2. Stability of Cohesive Soils behind Verfical Openings in Sheet Plle Walls. Analysis of a Recent Failure.

B. Broms & H. Bennermark

References

Related documents

While trying to keep the domestic groups satisfied by being an ally with Israel, they also have to try and satisfy their foreign agenda in the Middle East, where Israel is seen as

The EU exports of waste abroad have negative environmental and public health consequences in the countries of destination, while resources for the circular economy.. domestically

This study presents a review of the existing prediction models for vibrations caused by pile and sheet pile driving and is part of an on-going research project aiming for better

As part of their study of ground vibrations caused by vibratory sheet pile driving, Athanasopoulos and Pelekis (2000) reconstructed particle displacement paths from field

When determining the fineness number, the variation of the shear strength with the water content has been established with remoulded soils in both plastic a nd

46 Konkreta exempel skulle kunna vara främjandeinsatser för affärsänglar/affärsängelnätverk, skapa arenor där aktörer från utbuds- och efterfrågesidan kan mötas eller

The increasing availability of data and attention to services has increased the understanding of the contribution of services to innovation and productivity in

Närmare 90 procent av de statliga medlen (intäkter och utgifter) för näringslivets klimatomställning går till generella styrmedel, det vill säga styrmedel som påverkar