IMPORTANT
NOTICE
UNITED STATES
DEPARTMENT OF THE INTERIOR BUREAU OF RECLAMATION
Advance Notice Denver, Colorado, September 20, 1961.
To all prospective bidders for construction of Blue Mesa Dam and Power-plant, Curecanti Unit, Gunnison Division, Colorado River Storage Project.
It is anticipated that invitation for bids for construction of Blue Mesa Dam and Powerplant will be issued in December 1961.
Inasmuch as weather conditions at the time of issuance of specifications may make access to and examination of the site of the proposed work difficult, prospective bidders are invited to inspect the site in the near future, in order that they will be informed and in a position to submit a bid when the work is advertised. The approximate location of the work is shown on the attached location map.
The work will consist of construction of an earthfill dam 350 feet high and 800 feet long at the crest with a 16-foot diameter outlet tunnel, a 21-foot-diameter spillway tunnel, a powerplant constructed for installat10n of two 30, 000-kilowatt generating units, construct10n of 1. 1 miles of powerplant service road, and relocation of 4. 7 miles of State Highway No. 92. The generating units will be installed under a separate contract.
The principal items of work and the approximate quantities are as follows: 700, 000 cu yd 61. 000 cu yd 1, 000, 000 cu yd 2, 100, 000 cu yd 30, 000 cu yd 25, 000 cu yd 4,000,000 pounds 1, 000,000 pounds 900 lin ft
Excavation in open cut Excavation in tunnels
Earthfill in dam embankment
Rock and gravel fill in dam embankment Concrete in structures
Concrete in tunnel linings Reinforcing steel
Structural steel
Steel penstock, 16-foot-diameter Time allowed for completion: 1, 400 days.
The quantities listed above will necessarily be revised as detail plans and specifications are completed.
Prospective bidders wishing to visit the site are advised to contact James D. Seery, Project Construction Engineer, Bureau of Reclamation, Post Office
Box 179, Gunnison, Colorado.
Attachment
2
GRANT BLOODGOOD Assistant Commissioner and Chief Engineer
R 94W R 93W R 91W R90W R 69W R.88W R.87W R 66W SCALE OF lollLES EXPLANATION PAVfO UNCLASSIFIED UNITED STATES
0£,-,UtTMENT o, THE INTElflOlt
BUREAU OF lfECLAMATION
R &5W
COLORADO RIVER STORAGE PROJECT GVNNISON OIVISION-CVRECANTI VNIT·COLO/IIAOO
BLUE MESA DAM
KEY MAP LOCATION MAP
OltfAWN- WW o ___ auetwlTTEO- - - --- ' " ' - - - • - • • - · - - - -...
----W ----W ·- /lt6CQMMEfVOED- - - - -
-CH~CKEO
OENVElt,CQL.OltAOO