• No results found

Artificial ground-water recharge on the Arikaree River near Cope, Colorado: completion report

N/A
N/A
Protected

Academic year: 2021

Share "Artificial ground-water recharge on the Arikaree River near Cope, Colorado: completion report"

Copied!
17
0
0

Loading.... (view fulltext now)

Full text

(1)

7/17

e~

.

-c..~

R l

8-{p9

--l

to

·

- •

·Artificial Ground-Water

Recharge

a

-

On The Arikaree River

Near Cope, Colorado

CIVIL ENGINEERING DEPARTMENT

Engineering Research Center

Colorado State University

\ Fort Collins, Colorado

(2)

ARTIFICIAL GROUND WATER RECHARGE ON THE ARIKAREE RIVER NEAR COPE, COLORADO

by

J. Brookman(l) and D. K. Sunada( 2 )

INTRODUCTION

This project was initiated July 1, 1964, to study the feasibility of recharging excess or flood waters to an uncon-fined aquifer. The study included the selection of a site; design, construction, and maintenance of structures; data collection, analysis, and economic evaluation of artificial recharge.

An area on the Arikaree River near Cope, Colorado, was selected for the study. This area has an aquifer of very permeable medium and a large unsaturated thickness. The intermittant stream flows are associated with summer thunder-storm activity resulting in only one or two flows per year. The topography is gently rolling and the climate semi-arid with an annual precipitation of 16 inches. The watershed area above the study site is approximately 582 square miles. Principle irrigated crops near the study area are alfalfa hay, corn, and forage sorghums.

(1) Senior Research Technician, Civil Engineering Department Colorado State University, Fort Collins, Colorado

(2) Assistant Professor, Civil Engineering Department, Colo-rado State University, Fort Collins, ColoColo-rado.

CER68-69JB-DKS16

ll

ll

l

l

l~

Mlllll

i

l l

i

ll

l

l

!

II

I

IIIHlll!llll~

l

l

l

l

li

l

l

I

I

(3)

HISTORY OF PROJECT

Research Sponsors

The 44th General Assembly of Colorado Legislature

appropriated $10,000 to the Ground Water Commission for use

in fiscal year 1965. These funds were used for construction

and instrumentation of the study site. The appropriation

was requested by the Ground Water Commission and residents near Cope who asked that the study be located in their area to develop means of supplementing an inadequate irrigation water supply. The Cope Soil Conservation District encour-aged the study, offered to act as sub-contracting agency for construction, and pledged support to obtain easements

from land owners for the necessary sites.

Contracts for the Study

The Ground Water Commission contracted with the Civil Engineering Department at Colorado State University to select recharge sites, design structures, supervise construction,

collect and analyze data, and evaluate the results of the

study. The Commission subcontracted with the Cope Soil

Conservation District for construction costs. Funds were

allocated for three succeeding years to maintain the

struc-tures and evaluate the recharge benefits.

Site Selection

Preliminary investigation indicated several possible

(4)

investigations, two sites, indicated on Fig. 1, were selected.

Site 1 is located on a large curve in the river channel and

Site 2 is located below the confluence of the Arikaree River

and Gordon Creek. Test holes drilled to bedrock indicated no impermeable layers to prevent vertical movement of water in the aquifer. A thickness of 20 feet between land surface and the water table existed for recharge.

Design of Structures

One principle objective of the study was to develop an inexpensive recharge facility. Use of materials existing at the site for earth fill dams and existing topography

and vegetation for erosion control in the spillways provided an inexpensive recharge area.

Figure 2 shows a sketch of structures on Site 1. Dams D-1, D-2, and D-3 divert flow from the original channel and spread the flow over a large area for infiltration. Dikes I-1, I-2, and I-3 control the flow and reduce velocities while forcing a meandering pattern. The dikes prevented development of a new channel and provided some protection

for existing irrigation wells.

Construction

Funds for construction of the earth dikes were awarded, by the Ground Water Commission through the Cope Soil

Conser-vation District to a local contractor.

Specifications for the dams were for a 3:1 slope on

(5)

1

2:1 up and down slope and a three foot top. Compaction

was limited to that which occurred as fill was pushed into

place with a bulldozer. A t en percent over-fill was

speci-fied to allow for settlement .

Instrumentation

Estimates of the volume of water recharged were computed

from the change in ground water levels during and following

each recharge period. Data for Site 1 was obtained from

ten observation wells and six existing irrigation wells.

Ten wells were drilled and cased, seven of which were cased

with one and one-fourth inch pipe, and three with five inch

pipe. The five-inch wells were equipped with continous water

level recorders. Water levels in all wells were measured

periodically with a steel tape.

A continuous recorder was placed on a county highway

bridge about six miles upstream of the project area. Records

on periods of stream flow were collected from May 19 to June

30, 1965. The July 24, 1965, flood destroyed the bridge,

recorder, and 24 days of record.

OPERATION OF THE RECHARGE PROJECT

Flow Periods

The continuous recorder six miles upstream of the

re-charge site recorded flows during May and June 1965. Table

1 shows recorded flow periods and indicates whether water

(6)

l

24, 1965, flood was not possible but two slope-area

calcu-lations based on high water marks indicated discharge at

approximately 18,000 cfs. Flows during the July 25-30,

1965, period were estimated at two different times from

2,000 to 3,000 cfs.

Recharge by Structures

Flows during June 1965 did not exceed the design flows

of 1500 to 2000 cfs to significantly damage the structures

but did provide a significant amount of water for recharge.

The flood of July 1965 did considerable damage to most structures but also removed a considerable amount of

accumulated sediment. Flows occurred in August 1966, July

1967, and August 1968. The flow in July 1967 breached

dike I-3 which was repaired before the 1968 flow. The

total amount of water recharged in the period 1964-1968 was about 1810 acre feet.

EFFECTS ON WATER LEVELS

Water Levels Prior to Recharge

A water table map shown in Fig. 7 was drawn for June 16, 1965, prior to any significant flow. The map shows the

water table sloped toward the north-east with no apparent

influence from the river. Water levels were declining in

all observation wells and pumps on irrigation wells near the

project area were breaking suction after short periods of

(7)

Effect of Recharge

Water levels were measured several times daily during and immediately after flows occurred in the river. Figure

11 shows six representative water level hydrographs. Note the water levels drop steadily after the peak of recharge indicating lateral spreading and down valley movement. A water table contour map, Fig. 8, drawn for June 28, 1965, shows considerable change from June 16, and sloped sharply downward to the east and northeast. Water table maps drawn for later flows show very similar effects.

Quantity of Water Recharged

After each flow, a change in saturated thickness map was prepared to show the effect of recharge. A planimeter was used to determine the volume of aquifer that was saturated as the water level rose. Assuming a porosity of 20 percent, the estimated volume of recharge was computed. Table 2

gives dates and amounts of water recharged. Cross sections, Figs. 12-16, show the size and shape of the recharge mounds.

PROBLEMS ENCOUNTERED

Design for Large Floods

It is economically not feasible to design earth dikes to safely retain large floods. A complete watershed program, however, consisting of many small recharge facilities placed through the entire drainage might prevent such floods, re-charge more water, and prevent massive soil erosion.

(8)

Sediment Deposit

Flood waters deposited large volumes of sediment in

the recharge area. The coarser material was trapped behind

the first structure and finer sediments settled over lower parts of the facility - thus sealing the bed and reducing

rates of recharge. Removing these sediment deposits after every flow would be required to maintain high rates of re-charge. The flood of July 1965 effectively removed 9-12

inches of sediment, but also removed most of the other structures too.

EVALUATION OF THE STUDY

Demonstrational Purposes

The Cope recharge study has shown that artificial re-charge from emphemeral streams with flood flows is possible and practical. The rise in water levels restored nearby irrigation wells to year-around production. The design and

construction of the diversion structures was satisfactory; and installation costs were reasonable.

Cost-Benefit Analysis

During the life of the study, 1810 acre feet of water

were recharged at a construction and maintenance cost of

$13,140.00 or a cost of $7.26 per acre-foot. Assuming a

return value of ten dollars per acre-foot, as this water

was available to mature a crop, the study was a financial

(9)

The recharge structures are still effective and the

Cope site should provide additional recharge to the aquifer,

thereby reducing the cost per acre-foot of recharged water.

SUMMARY AND RECOMMENDATIONS

Inexpensive and expendable structures for artificial recharge were designed and constructed on the Arikaree River near Cope, Colorado, during 1964 and 1965. Flood

flows during the study provided approximately 1810 acre-feet of recharged water.

Recharge benefits in this study exceeded the cost of

construction and maintenance, and demonstrated that artificial

recharge is practical and that similar installations could be constructed in other areas of Colorado to obtain maximum use of water resources. Further study is needed to deter-mine a method of preventing the deposition of sediment and the resulting restricted recharge rates. Water Conservancy

and Management Districts, Soil Conservancy Districts, and

State Water Commissions should consider artificial recharge as a means of conserving and using all available water

(10)

ACKNOWLEDGMENTS

Appreciation is expressed to the State of Colorado and

the Colorado Ground Water Commission for the financial support

that made the study possible. Cooperation by the Cope Soil Conservation District, Ezra Page, Oscar Higgason, Lynn

Laybourn, Fred Laybourn, and other residents near Cope was greatly appreciated. Funds provided under the Federal Disaster Act and administered by the Army Corps of Engineers

were used to reconstruct the project after the July 1965 flood.

Other publications on the project include:

Longenbaugh, Robert A., PR 170, Progress Report - Artifi cial Water Recharge on the Arikaree River near Cope, Col

o-rado, July 1965.

Longenbaugh, Robert A., Experiment Station Report CER66RAL35,

Artificial Ground Water Recharge on the Arikaree River near Cope, Colorado, June 1966.

(11)

Date May 22 May 26 Jur_e 4 Jure 5 Jur_e 13 Jur1e 16 June 17 June 19 June 23 June 24 July 24 July 25 to July 30

.

TABLE 1 - FLOW PERIODS FOR THE ARIKAREE RIVER IN 1965

Length of Estimated Peak Water

flow--hrs Discharge-cfs Site No. 1

14 380 Yes 7 80 No 7 150 No 20 110 No 5 100 No 9 350 Yes 20 1000 Yes 10 30 Yes 6 290 Yes 20 1600 Yes 19 18,000 Yes inter- Yes mitt-ent

TABLE 2 - BEGINNING FLOW DATES AND AMOUNTS OF WATER RECHARGED

Reached Site No No No No No No Yes Yes No Yes Yes Yes

Date Acre-Feet Water Recharged

June 16, 1965 450 July 24, 1965 108 August 18, 1966 391 July 16, 1967 774 August 10, 1968 87 TOTAL 1810 No. 2

(12)

SCALE Of NILES 2 > Figure 1. Figure 3. Figure 5. ,

.

...

L.;

"I-I •

~,

••

[

J

15

r

/

.

//

Figure 2. Figure 4.

e OBSERVATION WELL

.a. WATER LEVEL REIXlRllER

RECHARGE STRUCTURE ~ STREAM LOCATION SCALE: 0 660 1320 1980 2640 FEET o!"'"'-oiiiii:::::::::=:=;j,V 4

----===;:!~

IIILE

Figure 1. Location of Cope recharge study area.

Figure 2. Sketch of site No. 1 showing

orientation of structures.

Figure 3. View looking northeast across site No. 1 prior to construc-tion.

Figure 4. Water impounded behind dam

0-1 site No. 1 after June

18 flow.

Figure 5. Flood flow destroying

struc-tures at site No. 1 on July

(13)

Figure 6. • Figure E. Figure

::.

o.

..

e OBSERVATION WELL

WATER LEVEL REC<ffl:ER

STREAM LOCATION S C ALE N 0 660 1320 198() 2640 f'EET O~ -r/le:.=:::::';i"4----C:::==t~ Nil£

..

OBSERVATION WELL WATER LEVEL RECORDER

STREAM LOCATION 13.20 1980 Z640 FEET 114 ~ MILE Figure 7. N OBSERVATION WELL

..

WATER LEVEL RECORDER STREAM 1..0CATlON SCALE:

0 HO 1320 IMO 840 Fl:[T

o.!"""-ii:::=~,--ic::=:::=;,~ MILE

Figure 9.

Figure 6. View across site No. 1

showing deposit of fine

clay sediment.

Figure 7. Water table contour map

prior to flow in the river.

Figure 8. Water table contour map on

June 28 after flows in the

river on June 16 and 26, 1965

Figure 9. Map showing the rise in

water level between June

16 and June 28, 1965

Figure 10. Aerial view of site No. 1

(14)

f,-w w IL I a: w \i 3: 0 f,-:r Ii: w 0 5 10 15 20 25 10 15 20 20 25 30 20 2: 15 20 25 20 I I I I I I -1---+--+-+--+---lt---+--+-+---t-OBSERVATION WELL NO. 8 e ---- ---t---r----r-. -- ___ j..._ __ --- ---- ---- ,---~

I

\

I\J \

r i \ I\ ' ' \J 1 "-r--I I I I I I OBSERVATION WELL NO. 7 - i - - - - -. ---- ---...__

OBSERVATION WELL NO. 12

I

--- --- ··-·t-1'---

"---I ·• ... - ---i---- __

---

---

--',

..

,

\

-t--+--+-+--+---1-t+--+r--.--.t---t-OBSERVATION WELL NO. 15 -+--+-..+-' _---c-+--+---+-

-,--.n---t----r-··1---

-

t-L

I I

I

I

I I

"

'-.I '- OBSERVATION WELL NO. 13

1'---r--r--r-- ----

\

r,... __ r u--·---- --- --- -' i..,, ,J /\ ·,_ ... __ ---r--....

I

I ',A , OBSERVATION WELL NO. 4 I I,' '---

r

!

--

... t---t---r--r--- Ir--,-__,_ ___ -- ( l'--r-- --- I'~ 25,f--+-+-+--11--+-

-

---~LJ

-1-+--+--1-f--+-+-+----=--r-·:.:::--"!'=--+-+-=:::Jr-+-+-+--1=t==-===t==-+--==-c+=+--+---+++--+--+-+-+-+-+--+:=:::::t=+==+-d--1+-1+---+1'-..:.:-=-···1--J ---.._t---J I __

I

_____

--·-r--1) - -J

w-=~--~a=~=-=-=~----=~=

1965 1966

==-=~---=-~~-=-=~---==

1967 1968

~=

Figure 11. Representative well hydrographs for six observation

(15)

ARIKAREE RIVER 92 90 ~""'--=--- 28

''----

I

.

",,

I

88

',

I

86

"

I-

",j

uJ SECTION A-A

I

~ 84 z

I

0 82

I

~ :;:,.

I

~ 80 uJ uJ

I

....I ID 78

I

~

I

0: June 16-. uJ 76

I

~ 3:: HORIZONTAL SCALE : 330 660 990 1320 FEET v4 MILE 74

I

I

I

I

72

J

I

.;I

70

;J

.~1

"' J:

-

...

Figure 12. Cross sections for June 16, 28, July 22, 26, 1965.

A 90

--

----/ ... SECTION 8-8 / \ 28 88 / \ . .--June / I \ 86 I \ I-/ ~ / / I 84 / ~ I I

!

82 / / , / '

i

80 ____

,,,

_,,,,,.

26 A / , 0: 78 ~ 3:: 76 HORIZONTAL SCALE: 0 330 660 990 1-yo FEET 74 0 l/9 i,4 MILE 72 70

(16)

90 SECTION B-B A 88 86 I-l!l 84 lo. I z Q 82

!

August 13 ~ 80 j a: 78 ~ :I,: 76 HORIZONTAL SCALE : 0 330 660 990 13?0 FEET 0 1/9 V4 MILE ,...June 13 74 72 70

Figure 14. Cross sections for June 13 and August 13, 1966 .

• 90 88 SECTION B- B A I- 86 July 16 ~ I 84 z 0 I= ~ 82 ~ w HORIZONTAL SCALE : ~ so1 m ~ 0 330 660 990 •nc> FEET 0 1/9 '-'◄ MILE a: 78 w

i

76 A _,,.June 1 74 72 70

(17)

• 9C A 88 SECTION B-B 86

~

84 I ....-August 12 ~

~

82

j

80 ~ 78

1

76'. A HORIZONTAL SCAL£ : 330 660 990 l?f' FEET V9 l<~ Mil£ 74 72 70

Figure 16. Cross sections for May 24 and August 12, 1968

References

Related documents

Det bör också poängteras att när det gäller vem som rangordnades högst av Folksam Bjk och Uniflx med avseende på hur lätta de var att handha, dvs hur självklart det var att

Nacka Kommun med ERP‐system för administrativa uppgifter samt separata IT‐ system  för  övriga  verksamheten.  Intrum  Justitia  AB  med  arvsystem 

translated into one or more locations of a timed automaton corresponding to the parent composite mode. The resulting PartialTransformationResult object is very

Enligt slitage- mätningar i fält har denna massa slitits mer än massorna inom hållbarhetsklass 2 efter en vinter och är bortsliten i hjulspår efter två vintrar. Om man på en väg

The finding that children’s engagement both affects, and get affected by, staff responsiveness could indicate that children with lower engagement affect their staff. negatively and

Även osäkerheten kring mängden material som levereras gör att personalen inte vill använda all tillgänglig plats för motorblock till förmån för andra mer högfrekventa

Under arbetet så kommer detta beröras ytterligare och djupare men för att beröra varför Energimyndigheten planerar att genomföra denna förändring är för att skapa ett

informanterna i ungdomsrådet tar sitt ansvar genom att försöka bygga upp ett verkande råd genom att värva nya medlemmar, och som Maja och Kalle berättade, ”…att vi själva liksom