• No results found

UIE WG 2 power quality: the concept of process immunity time for the assessment of dip immunity of industrial processes (after the CIGRE/CIRED/UIE joint WG C4.110)

N/A
N/A
Protected

Academic year: 2022

Share "UIE WG 2 power quality: the concept of process immunity time for the assessment of dip immunity of industrial processes (after the CIGRE/CIRED/UIE joint WG C4.110)"

Copied!
2
0
0

Loading.... (view fulltext now)

Full text

(1)

UIE WG 2 POWER QUALITY: THE CONCEPT OF PROCESS IMMUNITY TIME FOR THE ASSESSMENT OF DIP IMMUNITY OF INDUSTRIAL PROCESSES

(AFTER THE CIGRE/CIRED/UIE JOINT WG C4.110)

S. Djokic (1) , K. Stockman (2) , M. Bollen (3) , K. Van Reusel (4) , R. Neumann (5) , P. Marteyn (6)

(1) The University of Edinburgh, UK

(2) Howest, Belgium

(3) Luleå University of Technology and STRI AB, Sweden

(4) Katholieke Universiteit Leuven, Belgium

(5) Qualitrol, UK

(6) Dow, Netherlands

ABSTRACT: In October 2009, UIE established Working Group 2 (WG2) to work in the area of Power Quality and to continue with the dissemination and further development of the results produced by the former joint CIGRE/CIRED/UIE WG C4.110. The final results of the work in UIE WG2 will be presented in May 2012 at the XVII UIE Congress in St. Petersburg, including the delivery of a Tutorial on Voltage Dip Immunity of Equipment and Installations, as well as the presentation of three papers on relevant topics. This abstract briefly summarizes one of the considered topics – the concept of the “process immunity time” (PIT), which was formulated specifically for the assessment of dip immunity of various processes in industry.

The full paper will discuss the PIT and its application in more detail.

INTRODUCTION

The Joint Working Group (JWG) C4.110, which was sponsored by CIGRE, CIRED and UIE, was active between 2006 and 2009. The JWG C4.110 has considered and discussed a number of aspects of immunity of equipment and installations against voltage dips, and produced a Technical Report/Brochure, which is distributed by both CIGRE and UIE, [1]. In order to continue with the dissemination and further development of the results produced by the JWG C4.110, the UIE established Working Group 2 (WG2) in the area of Power Quality in October 2009. This abstract briefly summarizes the concept of the “process immunity time”

(PIT), a methodology for the assessment of dip immunity of various processes, formulated specifically for the application in the industry sector.

PROCESS IMMUNITY TIME: THEORETICAL BACKGROUND AND DEFINITION The PIT concept is introduced and developed by JWG C4.110 and UIE WG2 as a practical method for quantifying the immunity of various industrial processes against voltage dips and short interruptions. The ultimate goal is to keep an industrial processes up and running during voltage dip and short interruption events, or at least to identify dips and interruptions that will cause the process to trip, in order to take the optimal measures for process recovery. The PIT links individual devices in the process with the relevant process parameter(s) on which these devices have an impact.

Figure 1. shows how the PIT is defined. Starting with the nominal process parameter value

p nom (controlled by the device), a supply voltage interruption is assumed to occur at t 1 . As a

result, the process parameter starts to deviate from its nominal value. This usually happens

after a time interval t, which represents tripping of the device t seconds after the supply

interruption occured. At time t 2 , the process parameter value crosses the lower boundary p limit ,

below which normal operation of the process cannot be maintained, and process must be

either shut down, or re-started, or otherwise corrected.

(2)

a) b)

Figure 1. Process Immunity Time (PIT): a) definition, and b) successful restarting.

The PIT is defined as the time between the start of the voltage interruption or dip event (t 1 ) and the moment (t 2 ) at which relevant process parameter goes outside the allowed tolerance limit: PIT= t 2 - t 1 . Regarding the PIT values, industrial processes can be roughly divided in two groups: a) processes with high PIT value, characterised by a slow change of process parameters after a dip or interruption caused tripping (e.g .processes where critical parameters are pressure, temperature, tank levels, etc.); and b) processes with low PIT value, with parameters changing quickly after a dip/interruption caused tripping (e.g. processes with tight torque, speed or position control, etc.). The terms “high” and “low” PIT values are related to the duration of voltage dip/interruption events, which is typically up to a few seconds. In first case (high PIT), the critical device can be shut down and disconnected after the occurence of a dip/interruption event, and then re-started in a fully controllable way after the voltage supply recovers, Figure 1b. In the second case (low PIT), the relevant process parameter will quickly go outside the allowed limits after the tripping of a critical device. As the controlled shut down and restart is not an option, the tripping of the device should be prevented by improving its dip immunity (i.e. by improving so called dip “ride-through” equipment capabilities).

THE ASSESSMENT OF PROCESS IMMUNITY TIME

The PIT assessment procedure starts with listing all equipment and devices in the process.

Afterwards, the process is split-up in functional units (i.e. functions) or levels. The lowest level contains individual equipment and devices, for which affected process parameters should be identified. Higher levels contain sub-processes and bigger parts of the process. In that way, a database containing all relevant devices, functions and sub-processes of the considered process is established, indicating the corresponding PIT values for every combination of ‘piece of equipment’ and ‘process parameter’. Finally, by prioritising the PITs based on their durations, critical pieces of equipment within the process can be identified.

Due to the space limitation, this abstract provides a brief summary of the PIT concept and its application in industry sector. The final version of the paper will provide a more detailed discussion and also illustrate the PIT methodology on a number of representative examples.

CONCLUSION

The proposed paper will discuss the PIT concept, which is introduced and developed by JWG C4.110 and UIE WG2 as a practical method for understanding the behaviour of an industrial process during and immediately after a voltage dip or short interruption event.

REFERENCES

1. CIGRE/CIRED/UIE Joint Working Group C4.110 Voltage dip immunity of equipment and installations// CIGRE Technical Brochure TB No. 412. April 2010. [Available Online]

http://www.uie.org/powerquality, http://www.e-cigre.org/

= t

2

- t

1

References

Related documents

The headlines shall be: Introduction, Purpose and boundaries, Process overview, Rules, Connections and relations, Roles and responsibilities, Enablers, Measurements, Complete

The following main recommendations are formulated by the UIE WG2 to the equipment manufacturers: a) voltage dip immunity should be considered at an early stage of design and

The JWG C4.110 and its successor, UIE WG2, produced a number of important results related to the assessment and improvement of voltage dip immunity of equipment and

Trots att detta faktorer inte är kopplade till vår problemdiskussion så ansåg vi de ändå vara relevanta för att kunna förstå hur andra faktorer på arbetsplatsen kunde

För det tredje har det påståtts, att den syftar till att göra kritik till »vetenskap», ett angrepp som förefaller helt motsägas av den fjärde invändningen,

In this research, we conducted 19 semi-structured interviews of which five were held with public incubators, four with private incubators, nine with incubatees and one

In the existing literature about reading and solving mathematical tasks, we find that articles tend to focus on properties of the task text (a linguistic perspective),

Det viktiga i resonemangen med förberedelseklass och svenska som andraspråk är att skolan inte slentrianmässigt placerar alla elever i en grupp utan att reflektera över om